Permit: T22CM04738
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
4842 S MOUNTAIN AV
Address NEW:
4842 S MOUNTAIN AV
Apply Date:
06/23/2022
Applicant:
Description:
R-Roof Mount PV with Production Meter and AC Disco
Permit Reviews
Permit Number - T22CM04738
Permit Status: Issued
Permit Description: R-Roof Mount PV with Production Meter and AC Disco
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2022 | OTHER | 07/07/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM04738
Permit Status: Issued
Permit Description: R-Roof Mount PV with Production Meter and AC Disco
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/07/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T22CM04738
Permit Status: Issued
Permit Description: R-Roof Mount PV with Production Meter and AC Disco
| Date | Description | Comments |
|---|---|---|
| 06/23/2022 | THE INSTALLATION SHALL COMPLY WITH ALL APPLICABLE REQUIREMENTS OF SECTION 605.11.1 THROUGH 605.11.4 OF THE 2012 EDITION OF THE INTERNATIONAL FIRE CODE, THE INTERNATIONAL BUILDING CODE AND NFPA 70. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM04738
Permit Description: R-Roof Mount PV with Production Meter and AC Disco
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/22/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE INCR/POWERKILL} | |
| 09/22/2022 | COT - RSEL - Service Upgrade | Passed | {Activity date: 09/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, INCR Clearance was called into TEP at 10:55am Natalie (power-kill)} | |
| 09/30/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/30/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - 1090} | |
| 09/30/2022 | RSBU - Building Final | Passed | {Activity date: 09/30/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
| 09/30/2022 | BULD - Electrical Clearance | Passed | {Activity date: 09/30/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - CODE DGC} | |
| 09/30/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 09/30/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, please send DGC Clearance to TEP for the solar meter } |