Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
06/21/2022
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKF55I T21-M0086

Permit Reviews

Permit Number - T22CM04678
Permit Status: Complete
Permit Description: SFR RKF55I T21-M0086
Start Date Submittal Complete Date Status  
07/28/2022 OTHER 08/05/2022 COMPLETED Review Details
06/28/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/29/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM04678
Permit Status: Complete
Permit Description: SFR RKF55I T21-M0086
Date Description Comments
06/21/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
06/21/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
06/21/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
06/21/2022 NO FINAL UNTIL THE DISCHARGE AUTHORIZATIONFOR #P21SD00033 IS ISSUED BY PDEQ

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04678
Permite Description: SFR RKF55I T21-M0086
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
03/28/2023 COT - RSPL - Gas Pressure Test N/A Re-inspection required March 28th: framing at kitchen bearing wall incorrect, fill gap in AC platform, add stud to over notch bearing wall stud in dining room
03/28/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required March 28th: framing at kitchen bearing wall incorrect, fill gap in AC platform, add stud to over notch bearing wall stud in dining room
03/07/2023 COT - RSEL - Construction Power N/A Re-inspection required No address tag on door of main panel
10/27/2022 COT - RSEL - Outdoor Lighting N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready
COT - FCON - Fire - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04678
Permit Description: SFR RKF55I T21-M0086
Total Completed Inspections - 25
Date Description Inspector Results Comments
09/21/2022 COT - RSPL - Rough Soil Passed {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
10/04/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott

}
10/04/2022 COT - RSBU - Preslab Passed {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott

}
10/04/2022 COT - RSEL - Electrical Underground Passed {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott

}
10/04/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott

}
11/07/2022 COT - RSBU - Roof Nailing Passed
02/03/2023 COT - RSPL - Sewer Passed
03/15/2023 COT - RSPL - Yard Water Line Passed
03/28/2023 COT - LCPL - Plumbing Intermediate Passed
03/28/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
03/30/2023 COT - RSPL - Gas Pressure Test Passed
03/30/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
03/30/2023 COT - LCBU - Framing Passed
04/18/2023 COT - HCBU - Interior Shear Bracing Passed
05/09/2023 COT - RSEL - Construction Power Passed 5/9/23: TEP ECO
05/09/2023 BULD - Electrical Clearance Passed 5/9/23: TEP ECO
05/26/2023 COT - RSEL - Outdoor Lighting Passed
06/22/2023 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 6/22/2023
06/28/2023 COT - RSPL - Plumbing Final Passed
06/28/2023 ENGR Engineering Final Passed
06/28/2023 COT - RSME - Mechanical Final Passed
06/28/2023 COT - RSEL - Electrical Final Passed
06/28/2023 RSBU - Building Final Passed
06/28/2023 RSME - Mechanical Progress Passed
06/30/2023 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SITE PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT_1-2023-06-29_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW