Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM04678
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
12764 E TORTOISE POINTE PL
Address NEW:
12764 E TORTOISE POINTE PL
Apply Date:
06/21/2022
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKF55I T21-M0086
Permit Reviews
Permit Number - T22CM04678
Permit Status: Complete
Permit Description: SFR RKF55I T21-M0086
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/28/2022 | OTHER | 08/05/2022 | COMPLETED |
| 06/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/29/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM04678
Permit Status: Complete
Permit Description: SFR RKF55I T21-M0086
| Date | Description | Comments |
|---|---|---|
| 06/21/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 06/21/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
| 06/21/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 06/21/2022 | NO FINAL UNTIL THE DISCHARGE AUTHORIZATIONFOR #P21SD00033 IS ISSUED BY PDEQ |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04678
Permite Description: SFR RKF55I T21-M0086
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/28/2023 | COT - RSPL - Gas Pressure Test | N/A | Re-inspection required | March 28th: framing at kitchen bearing wall incorrect, fill gap in AC platform, add stud to over notch bearing wall stud in dining room |
| 03/28/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | March 28th: framing at kitchen bearing wall incorrect, fill gap in AC platform, add stud to over notch bearing wall stud in dining room |
| 03/07/2023 | COT - RSEL - Construction Power | N/A | Re-inspection required | No address tag on door of main panel |
| 10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04678
Permit Description: SFR RKF55I T21-M0086
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
| 10/04/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott } |
|
| 10/04/2022 | COT - RSBU - Preslab | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott } |
|
| 10/04/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott } |
|
| 10/04/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/28/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - Cancel all inspections per Scott } |
|
| 11/07/2022 | COT - RSBU - Roof Nailing | Passed | ||
| 02/03/2023 | COT - RSPL - Sewer | Passed | ||
| 03/15/2023 | COT - RSPL - Yard Water Line | Passed | ||
| 03/28/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 03/28/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 03/30/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
| 03/30/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 03/30/2023 | COT - LCBU - Framing | Passed | ||
| 04/18/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 05/09/2023 | COT - RSEL - Construction Power | Passed | 5/9/23: TEP ECO | |
| 05/09/2023 | BULD - Electrical Clearance | Passed | 5/9/23: TEP ECO | |
| 05/26/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 06/22/2023 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 6/22/2023 | |
| 06/28/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 06/28/2023 | ENGR Engineering Final | Passed | ||
| 06/28/2023 | COT - RSME - Mechanical Final | Passed | ||
| 06/28/2023 | COT - RSEL - Electrical Final | Passed | ||
| 06/28/2023 | RSBU - Building Final | Passed | ||
| 06/28/2023 | RSME - Mechanical Progress | Passed | ||
| 06/30/2023 | COT - FCON - Fire - Final | Passed |