Permit: T22CM04651
Permit Details
Apply Date:
06/21/2022
Applicant:
Description:
Fire Damage Repair in units 261 and 263
Permit Reviews
Permit Number - T22CM04651
Permit Status: Complete
Permit Description: Fire Damage Repair in units 261 and 263
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/21/2022 | OTHER | 08/06/2022 | COMPLETED |
10/13/2022 | RESUBMITTAL | 10/13/2022 | ACTIVE |
12/30/2022 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 12/30/2022 | APPROVED |
10/28/2022 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 11/09/2022 | REQUIRES RESUBMIT |
11/28/2022 | COMMERCIAL PDSD SIMPLE REVIEW v.2 | 12/06/2022 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04651
Permit Description: Fire Damage Repair in units 261 and 263
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/21/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/21/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
04/03/2023 | COT - LCBU - Framing | Passed | 4-3-23: Corrections completed, Firewall Inspection added to comply with IBC 420.2, 708, 708.3, 708.4#2, and Table 721.1(2)#14-1.3. | |
04/03/2023 | COT - LCEL - Electrical Intermediate | Passed | 4-3-23: Corrections completed, Firewall Inspection added to comply with IBC 420.2, 708, 708.3, 708.4#2, and Table 721.1(2)#14-1.3. 4-3-23: Corrections c |
|
04/03/2023 | COT - LCEL - Electrical Above Ceiling | Passed | 4-3-23: Corrections completed, Firewall Inspection added to comply with IBC 420.2, 708, 708.3, 708.4#2, and Table 721.1(2)#14-1.3. | |
04/13/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
04/13/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
04/13/2023 | COT - LCEL - Electrical Reconnect | Passed | ||
04/13/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
05/26/2023 | COT - LCBU - Building Final | Passed | Construction is complete. Okay to issue Certificate of Occupancy for Units 261 & 263. | |
05/26/2023 | COT - LCEL - Electrical Final | Passed | Electrical panels are properly labeled. AFCI Breakers are installed for bedrooms. GFCI outlets are installed in kitchen and bathroom. Ceiling lights are installed and operational. | |
05/26/2023 | COT - LCME - Mechanical Final | Passed | A/C Units are installed and operational. | |
05/26/2023 | COT - LCPL - Gas Final | Passed | Gas valve installed for stoves. | |
05/26/2023 | COT - LCPL - Plumbing Final | Passed | All bathroom and kitchen plumbing fixtures are installed and operational. |