Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/21/2022
Applicant:
Description:
Fire Damage Repair in units 261 and 263

Permit Reviews

Permit Number - T22CM04651
Permit Status: Complete
Permit Description: Fire Damage Repair in units 261 and 263
Start Date Submittal Complete Date Status  
06/21/2022 OTHER 08/06/2022 COMPLETED Review Details
10/13/2022 RESUBMITTAL 10/13/2022 ACTIVE Review Details
12/30/2022 COMMERCIAL PDSD SIMPLE REVIEW v.1 12/30/2022 APPROVED Review Details
10/28/2022 COMMERCIAL PDSD SIMPLE REVIEW v.1 11/09/2022 REQUIRES RESUBMIT Review Details
11/28/2022 COMMERCIAL PDSD SIMPLE REVIEW v.2 12/06/2022 APPROVED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04651
Permit Description: Fire Damage Repair in units 261 and 263
Total Completed Inspections - 14
Date Description Inspector Results Comments
03/21/2023 COT - LCPL - Plumbing Intermediate Passed
03/21/2023 COT - LCME - Mechanical Intermediate Passed
04/03/2023 COT - LCBU - Framing Passed 4-3-23: Corrections completed, Firewall Inspection added to comply with IBC 420.2, 708, 708.3, 708.4#2, and Table 721.1(2)#14-1.3.
04/03/2023 COT - LCEL - Electrical Intermediate Passed 4-3-23: Corrections completed, Firewall Inspection added to comply with IBC 420.2, 708, 708.3, 708.4#2, and Table 721.1(2)#14-1.3.

4-3-23: Corrections c
04/03/2023 COT - LCEL - Electrical Above Ceiling Passed 4-3-23: Corrections completed, Firewall Inspection added to comply with IBC 420.2, 708, 708.3, 708.4#2, and Table 721.1(2)#14-1.3.
04/13/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
04/13/2023 COT - LCPL - Gas Pressure Test Passed
04/13/2023 COT - LCEL - Electrical Reconnect Passed
04/13/2023 COT - LCEL - Outdoor Lighting Passed
05/26/2023 COT - LCBU - Building Final Passed Construction is complete. Okay to issue Certificate of Occupancy for Units 261 & 263.
05/26/2023 COT - LCEL - Electrical Final Passed Electrical panels are properly labeled. AFCI Breakers are installed for bedrooms. GFCI outlets are installed in kitchen and bathroom. Ceiling lights are installed and operational.
05/26/2023 COT - LCME - Mechanical Final Passed A/C Units are installed and operational.
05/26/2023 COT - LCPL - Gas Final Passed Gas valve installed for stoves.
05/26/2023 COT - LCPL - Plumbing Final Passed All bathroom and kitchen plumbing fixtures are installed and operational.

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
T22CM04651 PERMIT.PDF DOCUMENTS VIEW
APPLICATION_V1_V1.PDF DOCUMENTS VIEW
CONS-PLAN SET_MIDTOWN ON SENECA UNITS 261 AND 263_V2_V1.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS_MIDTOWN ON SENECA UNITS 261 AND 263_V1_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_PLAN SET_MIDTOWN ON SENECA UNITS 261 AND 263_V2.PDF DOCUMENTS VIEW