Permit: T22CM04573
Permit Details
Apply Date:
06/18/2022
Applicant:
John Mancini
Description:
Replace evap coolers with ac, upgrade electrical panels with new distribution, replace existing elec This permit is for units A, B, C, D, E, F, G, H, I, J, K, L
Permit Reviews
Permit Number - T22CM04573
Permit Status: Complete
Permit Description: Replace evap coolers with ac, upgrade electrical panels with new distribution, replace existing elec This permit is for units A, B, C, D, E, F, G, H, I, J, K, L
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/18/2022 | OTHER | 07/18/2022 | COMPLETED |
08/23/2022 | RESUBMITTAL | 09/05/2022 | COMPLETED |
04/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/30/2024 | APPROVED |
Conditions
Permit Number - T22CM04573
Permit Status: Complete
Permit Description: Replace evap coolers with ac, upgrade electrical panels with new distribution, replace existing elec This permit is for units A, B, C, D, E, F, G, H, I, J, K, L
Date | Description | Comments |
---|---|---|
03/16/2024 | AIR BALANCE REPORT REQUIRED - EXHAUST ONLY | |
04/30/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04573
Permite Description: Replace evap coolers with ac, upgrade electrical panels with new distribution, replace existing elec This permit is for units A, B, C, D, E, F, G, H, I, J, K, L
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
03/14/2023 | COT - LCEL - Electrical Final | N/A | Partial Pass | New services approved for units G,H,I,J,K,L. Inspection partialled for future services. |
11/21/2023 | COT - LCME - Mechanical Final | N/A | Partial Pass | final inspection for units G, H, I, J, K, L |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04573
Permit Description: Replace evap coolers with ac, upgrade electrical panels with new distribution, replace existing elec This permit is for units A, B, C, D, E, F, G, H, I, J, K, L
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/20/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR # G, H, I, J, K, L on North building } |
|
12/05/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
02/01/2023 | COT - LCEL - Service Upgrade | Passed | ||
10/31/2023 | BULD - Electrical Clearance | Passed | New service, cutover for units A, B, C, D, E, F passed | |
10/31/2023 | COT - LCEL - Electrical Final | Passed | New service, cutover for units A, B, C, D, E, F passed | |
11/14/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
03/08/2024 | COT - LCME - Mechanical Final | Passed | ||
03/08/2024 | COT - LCEL - Outdoor Lighting | Passed |