Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/16/2022
Applicant:
Chris Dornhecker
Description:
7287 sq ft gas canopy.

Permit Reviews

Permit Number - T22CM04502
Permit Status: Complete
Permit Description: 7287 sq ft gas canopy.
Start Date Submittal Complete Date Status  
06/16/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 08/24/2022 COMPLETED Review Details
09/09/2022 RESUBMITTAL 09/20/2022 COMPLETED Review Details
10/12/2022 RESUBMITTAL 10/13/2022 ACTIVE Review Details
09/20/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/20/2023 REQUIRES RESUBMIT Review Details
12/11/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/11/2023 REQUIRES RESUBMIT Review Details
11/21/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 11/28/2023 APPROVED Review Details
12/18/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/21/2023 APPROVED Review Details
11/04/2022 COMMERCIAL REVIEW - FULL v.1 12/20/2022 APPROVED Review Details

Conditions

Permit Number - T22CM04502
Permit Status: Complete
Permit Description: 7287 sq ft gas canopy.
Date Description Comments
11/16/2022 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
11/16/2022 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
12/21/2022 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
11/16/2022 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
11/16/2022 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
11/16/2022 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
11/16/2022 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
11/16/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
11/16/2022 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04502
Permite Description: 7287 sq ft gas canopy.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
09/20/2022 COT - FCON - Tank - Final N/A Re-inspection required {Activity date: 09/20/2022; Status: Prior to Final Inspectn; Inspector: jvincent; Comment: Entered by JVINCEN1 - Contact Inspector Silva for permit questions regarding the operational permit for flammable combustible liquids and inspections at 5208377094, 5204199177}
11/17/2023 approved by Jesus Silva 9/28/23

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04502
Permit Description: 7287 sq ft gas canopy.
Total Completed Inspections - 19
Date Description Inspector Results Comments
03/13/2023 COT - HCPL - Plumbing Roof Drains Passed
03/14/2023 COT - HCEL - Electrical Progress Passed for canopy underground, ok to cover
06/21/2023 COT - HCEL - Electrical Above Ceiling Passed
08/15/2023 COT - HCPL - Plumbing Progress Passed
08/15/2023 COT - HCPL - Rough Soil Passed
08/15/2023 COT - HCBU - Roof Nailing Passed
08/15/2023 COT - HCBU - Excavation/Rebar/Zoning Passed
08/15/2023 COT - HCBU - Framing Passed
08/15/2023 COT - HCEL - Electrical Underground Passed
08/15/2023 COT - HCBU - Preslab Passed
08/15/2023 COT - HCPL - Plumbing Intermediate Passed
08/15/2023 COT - HCBU - Building Progress Passed
09/09/2023 COT - HCEL - Electrical Intermediate Passed
09/08/2023 SITE - Zoning Final Passed
09/09/2023 COT - HCEL - Outdoor Lighting Passed
09/20/2023 COT - HCBU - Building Final Passed 9/20/23:CofO
09/20/2023 COT - FCON - Fire - Final Passed
09/20/2023 COT - HCPL - Plumbing Final Passed
09/20/2023 COT - HCEL - Electrical Final Passed