Permit: T22CM04469
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
5489 S PARK AV BLDG 1 UNIT 1106
Address NEW:
5489 S PARK AV BLDG 1 UNIT 1106
Apply Date:
06/15/2022
Applicant:
Greg
Description:
Solar Panels
Permit Reviews
Permit Number - T22CM04469
Permit Status: Complete
Permit Description: Solar Panels
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/15/2022 | 3RD PARTY REVIEW - COMMERCIAL | 08/04/2022 | COMPLETED |
Conditions
Permit Number - T22CM04469
Permit Status: Complete
Permit Description: Solar Panels
| Date | Description | Comments |
|---|---|---|
| 08/04/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04469
Permit Description: Solar Panels
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2022 | COT - LCBU - Building Final | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 10/11/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 10/11/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 10/11/2022 | PDSD Building Division - TEP PMÂ Clearance | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE DGC} | |
| 10/11/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Clear dgc} |