Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM04465
Permit Details
Apply Date:
06/15/2022
Applicant:
Description:
TI: Retail/Office
Permit Reviews
Permit Number - T22CM04465
Permit Status: Complete
Permit Description: TI: Retail/Office
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/15/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/22/2022 | COMPLETED |
09/01/2022 | RESUBMITTAL | 09/22/2022 | COMPLETED |
01/11/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/11/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM04465
Permit Status: Complete
Permit Description: TI: Retail/Office
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
09/21/2022 | SPECIAL INSPECTION IS REQUIRED - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. |
09/21/2022 | SPECIAL INSPECTION IS REQUIRED - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. |
Conditions
Permit Number - T22CM04465
Permit Status: Complete
Permit Description: TI: Retail/Office
Date | Description | Comments |
---|---|---|
09/22/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04465
Permite Description: TI: Retail/Office
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Service Upgrade | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Temporary Service | N/A | Not Ready | |
12/15/2022 | COT - LCPL - Plumbing Final | N/A | Partial Pass | Field work complete, awaiting chlorination report approval. |
12/15/2022 | COT - LCME - Mechanical Final | N/A | Partial Pass | Field work complete; awaiting balance report approval. |
12/15/2022 | COT - LCBU - Roof Nailing | N/A | Not Applicable | N/A |
12/15/2022 | COT - LCBU - Building Final | N/A | Re-inspection required | Install grab bars and undersink protection for restroom. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04465
Permit Description: TI: Retail/Office
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/14/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/14/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE RECN SUITE #135} | |
10/14/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
10/18/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
11/28/2022 | COT - LCEL - Service Upgrade | Passed | Two meters cleared for suite 135; meters 2M and 1M. | |
11/29/2022 | COT - LCEL - Temporary Service | Passed | Two meters (1M and 2M) cleared for suite 135. | |
11/30/2022 | COT - LCEL - Electrical Progress | Passed | Added to enable viewing of inspection history from the field to obtain notes from previous two clearance inspections that were ineffective in transmitting field notes to TEP. | |
12/06/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
12/06/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/06/2022 | COT - LCME - Mechanical Progress | Passed | ||
12/06/2022 | COT - LCBU - Framing | Passed | ||
12/15/2022 | COT - FCON - Fire - Final | Passed | ||
12/15/2022 | COT - FCON - Sprinkler - Final | Passed | ||
12/15/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
12/15/2022 | COT - LCME - Mechanical Intermediate | Passed | ||
12/19/2022 | COT - LCBU - Building Final | Passed |