Permit: T22CM04344
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
2103 E MABEL ST
Address NEW:
2103 E MABEL ST
Apply Date:
06/11/2022
Applicant:
Description:
ADU Addition
Permit Reviews
Permit Number - T22CM04344
Permit Status: Issued
Permit Description: ADU Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/13/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 07/11/2022 | COMPLETED |
| 07/16/2022 | RESUBMITTAL | 07/26/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM04344
Permite Description: ADU Addition
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 07/20/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 07/20/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 07/20/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 12/02/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
| 12/02/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM04344
Permit Description: ADU Addition
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/23/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved. Okay to backfill.} | |
| 08/31/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 08/31/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 08/31/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/31/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 10/10/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 10/10/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 12/02/2022 | COT - LCBU - Framing | Passed | ||
| 12/02/2022 | COT - RSPL - Yard Water Line | Passed | ||
| 12/02/2022 | COT - RSEL - Electrical Underground | Passed | ||
| 12/08/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | corrections completed. | |
| 07/21/2023 | COT - RSME - Mechanical Final | Passed | ||
| 07/21/2023 | RSBU - Building Final | Passed | ||
| 07/21/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/21/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 07/21/2023 | COT - RSEL - Electrical Final | Passed |