Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/09/2022
Applicant:
Description:
TI: Retail Cookie Store

Permit Reviews

Permit Number - T22CM04279
Permit Status: Complete
Permit Description: TI: Retail Cookie Store
Start Date Submittal Complete Date Status  
06/09/2022 3RD PARTY REVIEW - COMMERCIAL TI 07/22/2022 COMPLETED Review Details
08/04/2022 RESUBMITTAL 08/04/2022 COMPLETED Review Details
10/20/2022 REVISION - - 1ST 10/20/2022 ACTIVE Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 11/28/2022 APPROVED Review Details
12/01/2022 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/01/2022 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T22CM04279
Permit Status: Complete
Permit Description: TI: Retail Cookie Store
Total Outstanding Activity Conditions - 1
Date Name
07/22/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Conditions

Permit Number - T22CM04279
Permit Status: Complete
Permit Description: TI: Retail Cookie Store
Date Description Comments
08/04/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04279
Permite Description: TI: Retail Cookie Store
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
12/01/2022 COT - LCBU - Building Progress N/A Partial Pass
12/01/2022 COT - LCEL - Electrical Final N/A Partial Pass

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04279
Permit Description: TI: Retail Cookie Store
Total Completed Inspections - 24
Date Description Inspector Results Comments
08/29/2022 COT - LCPL - Rough Soil Passed {Activity date: 08/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, connected to 4" main in building}
09/07/2022 COT - LCBU - Preslab Passed {Activity date: 09/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/29/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - INSPECTOR TG AP ON 08/29/22. INSPECTOR TL REQUESTED TO BE PLACED IN OPEN, HE ON SITE.}
09/23/2022 COT - LCBU - Framing Passed {Activity date: 09/23/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
09/28/2022 COT - LCPL - Sewer Passed {Activity date: 09/28/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, also verified with grease trap

} ; {Activity date: 08/29/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - INSPECTOR TG PLACED IN AP ON 08/29/22. INSPECTOR TL REQESTED OPEN, ON SITE.}
10/06/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to cover, pending above ceiling}
10/06/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to cover, pending above ceiling}
10/06/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved pending above ceiling}
10/14/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 10/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
10/19/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO/UNIT #170}
10/19/2022 COT - LCEL - Service Upgrade Passed {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - - Approved, please send ECO Clearance to TEP for unit #170, this is part of a meter pack}
11/04/2022 COT - LCBU - Building Above Ceiling Passed
11/04/2022 COT - LCME - Mechanical Above Ceiling Passed
11/04/2022 COT - LCPL - Plumbing Above Ceiling Passed
11/04/2022 COT - LCEL - Electrical Above Ceiling Passed
12/01/2022 COT - LCPL - Plumbing Final Passed
12/01/2022 COT - LCME - Kitchen Hood Passed no hood
12/01/2022 COT - LCEL - Electrical Reconnect Passed INSPECTION N/A
12/01/2022 COT - LCME - Mechanical Final Passed
12/01/2022 COT - FCON - Sprinkler - Final Passed
12/01/2022 COT - LCPL - Plumbing Progress Passed
12/01/2022 COT - FCON - Fire - Final Passed
12/02/2022 COT - LCBU - Building Final Passed recommend for C/O
12/02/2022 COT - LCBU - Building Progress Passed
12/02/2022 COT - LCEL - Electrical Final Passed