Permit: T22CM04279
Permit Details
Apply Date:
06/09/2022
Applicant:
Description:
TI: Retail Cookie Store
Permit Reviews
Permit Number - T22CM04279
Permit Status: Complete
Permit Description: TI: Retail Cookie Store
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/09/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/22/2022 | COMPLETED |
08/04/2022 | RESUBMITTAL | 08/04/2022 | COMPLETED |
10/20/2022 | REVISION - - 1ST | 10/20/2022 | ACTIVE |
10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/28/2022 | APPROVED |
12/01/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/01/2022 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM04279
Permit Status: Complete
Permit Description: TI: Retail Cookie Store
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/22/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T22CM04279
Permit Status: Complete
Permit Description: TI: Retail Cookie Store
Date | Description | Comments |
---|---|---|
08/04/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04279
Permite Description: TI: Retail Cookie Store
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
12/01/2022 | COT - LCBU - Building Progress | N/A | Partial Pass | |
12/01/2022 | COT - LCEL - Electrical Final | N/A | Partial Pass |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04279
Permit Description: TI: Retail Cookie Store
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/29/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, connected to 4" main in building} | |
09/07/2022 | COT - LCBU - Preslab | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 08/29/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - INSPECTOR TG AP ON 08/29/22. INSPECTOR TL REQUESTED TO BE PLACED IN OPEN, HE ON SITE.} | |
09/23/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
09/28/2022 | COT - LCPL - Sewer | Passed | {Activity date: 09/28/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, also verified with grease trap } ; {Activity date: 08/29/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - INSPECTOR TG PLACED IN AP ON 08/29/22. INSPECTOR TL REQESTED OPEN, ON SITE.} |
|
10/06/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to cover, pending above ceiling} | |
10/06/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to cover, pending above ceiling} | |
10/06/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved pending above ceiling} | |
10/14/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
10/19/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO/UNIT #170} | |
10/19/2022 | COT - LCEL - Service Upgrade | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - - Approved, please send ECO Clearance to TEP for unit #170, this is part of a meter pack} | |
11/04/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
11/04/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
11/04/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
11/04/2022 | COT - LCEL - Electrical Above Ceiling | Passed | ||
12/01/2022 | COT - LCPL - Plumbing Final | Passed | ||
12/01/2022 | COT - LCME - Kitchen Hood | Passed | no hood | |
12/01/2022 | COT - LCEL - Electrical Reconnect | Passed | INSPECTION N/A | |
12/01/2022 | COT - LCME - Mechanical Final | Passed | ||
12/01/2022 | COT - FCON - Sprinkler - Final | Passed | ||
12/01/2022 | COT - LCPL - Plumbing Progress | Passed | ||
12/01/2022 | COT - FCON - Fire - Final | Passed | ||
12/02/2022 | COT - LCBU - Building Final | Passed | recommend for C/O | |
12/02/2022 | COT - LCBU - Building Progress | Passed | ||
12/02/2022 | COT - LCEL - Electrical Final | Passed |