Permit: T22CM04228
Permit Details
Apply Date:
06/07/2022
Applicant:
Ashley Benjamin
Description:
Tenant Improvement within existing shell building. New covered patio.
Permit Reviews
Permit Number - T22CM04228
Permit Status: Complete
Permit Description: Tenant Improvement within existing shell building. New covered patio.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/07/2022 | OTHER | 07/26/2022 | COMPLETED |
| 01/06/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/19/2023 | APPROVED |
| 03/15/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/29/2023 | APPROVED |
Conditions
Permit Number - T22CM04228
Permit Status: Complete
Permit Description: Tenant Improvement within existing shell building. New covered patio.
| Date | Description | Comments |
|---|---|---|
| 06/07/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 06/07/2022 | FUP T21OT00558 MUST BE PAID BEFORE FINAL INSPECTIONS. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04228
Permit Description: Tenant Improvement within existing shell building. New covered patio.
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/29/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR #104} | |
| 08/29/2022 | COT - LCEL - Service Upgrade | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Clear incr #104 } |
|
| 09/02/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 09/02/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 10/14/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved NO CLEARANCE REQUIRED.} |
|
| 10/14/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Construction Power | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - HCBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Electrical Reconnect | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/14/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 01/11/2023 | COT - LCME - Mechanical Final | Passed | ||
| 01/11/2023 | COT - LCEL - Electrical Final | Passed | ||
| 01/11/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 02/01/2023 | TRSP - ROW - Final/Close-Out | Passed | There are no issues in the right of way for this address. | |
| 02/01/2023 | PDSD Building Division - Sign Final | Passed | ||
| 02/01/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
| 02/01/2023 | ENGR Engineering Final | Passed | ||
| 02/01/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 02/28/2023 | COT - FCON - Fire - Final | Passed | per cbass | |
| 02/28/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 02/28/2023 | COT - FCON - Sprinkler - Final | Passed | per cbass | |
| 02/28/2023 | COT - FCON - Alarm - Final | Passed | per cbass | |
| 02/28/2023 | COT - LCBU - Building Final | Passed |