Permit: T22CM04205
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
4811 E GRANT RD UNIT 113
Address NEW:
4811 E GRANT RD UNIT 113
Apply Date:
06/06/2022
Applicant:
Description:
TI: Restaurant
Permit Reviews
Permit Number - T22CM04205
Permit Status: Complete
Permit Description: TI: Restaurant
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/06/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/14/2022 | COMPLETED |
| 08/02/2022 | RESUBMITTAL | 08/05/2022 | COMPLETED |
| 09/02/2022 | REVISION - - 1ST | 09/14/2022 | COMPLETED |
| 11/29/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/30/2022 | APPROVED |
Conditions
Permit Number - T22CM04205
Permit Status: Complete
Permit Description: TI: Restaurant
| Date | Description | Comments |
|---|---|---|
| 08/04/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 08/04/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 08/04/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATINO REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
| 08/04/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
| 08/05/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04205
Permite Description: TI: Restaurant
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Hood System - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04205
Permit Description: TI: Restaurant
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/01/2022 | COT - LCBU - Preslab | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved. U G Plumbing.} | |
| 09/16/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/01/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Not Ready} | |
| 09/19/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/16/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Not Ready.} ; {Activity date: 09/01/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Not Ready} | |
| 09/21/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/16/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Partial Approval: OK to one side.} | |
| 09/21/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 10/17/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/16/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Partial Approval: Hard ducts.} | |
| 11/04/2022 | COT - LCPL - Gas Pressure Test | Passed | ||
| 11/04/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
| 11/04/2022 | COT - LCEL - Electrical Progress | Passed | ||
| 11/04/2022 | COT - LCPL - Plumbing Progress | Passed | ||
| 11/04/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 11/04/2022 | COT - LCME - Mechanical Progress | Passed | ||
| 11/04/2022 | COT - LCEL - Electrical Final | Passed | ||
| 11/04/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 11/04/2022 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 11/04/2022 | COT - LCBU - Building Progress | Passed | ||
| 11/08/2022 | COT - HCPL - Gas Pressure Test | Passed | ||
| 11/08/2022 | COT - HCEL - Electrical Final | Passed | ||
| 11/14/2022 | COT - LCBU - Building Final | Passed | ||
| 11/14/2022 | SITE - Zoning Final | Passed | N/A | |
| 11/14/2022 | COT - FCON - Alarm - Final | Passed | ||
| 11/14/2022 | COT - FCON - Fire - Final | Passed | ||
| 11/14/2022 | COT - FCON - Hood System - Final | Passed |