Permit: T22CM04201
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
4805 E SPEEDWAY BL
Address NEW:
4805 E SPEEDWAY BL
Apply Date:
06/06/2022
Applicant:
Vince Catalano
Description:
TI: Carneceria
Permit Reviews
Permit Number - T22CM04201
Permit Status: Complete
Permit Description: TI: Carneceria
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/06/2022 | COMMERCIAL - TI | 06/28/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04201
Permite Description: TI: Carneceria
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Canceled | {Activity date: 09/20/2022; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Not Applicable.} |
| 10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
| 10/26/2022 | COT - ENGR - Site - Assurance Release | N/A | Not Ready | health approved by PUrbina 1\14\2023 |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Kitchen Hood | N/A | Not Ready | |
| 02/02/2023 | COT - LCME - Mechanical Intermediate | N/A | Re-inspection required | approved plans not on site |
| 10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
| 02/02/2023 | COT - LCEL - Electrical Final | N/A | Re-inspection required | GFCI all outlets within 6 feet of sinks. Provide approved plans for inspection |
| 10/26/2022 | COT - FCON - Hood System - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
| 02/08/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | EM lights repaired, Fire extinguisher inspection report. |
| 02/02/2023 | COT - LCBU - Building Final | N/A | Re-inspection required | approved plans not on site. Fire,Health,Site Engineering have not signed off |
| 02/02/2023 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | approved plans not on site |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04201
Permit Description: TI: Carneceria
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/19/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/17/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Partial Approval: Grease trap.} | |
| 08/19/2022 | COT - LCPL - Sewer | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 09/20/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 09/20/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 09/20/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/19/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready } ; {Activity date: 08/17/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -Not Ready} |
|
| 02/02/2023 | COT - LCBU - Building Progress | Passed | ||
| 02/02/2023 | COT - FCON - Alarm - Final | Passed | ||
| 02/03/2023 | COT - LCEL - Electrical Final | Passed | ||
| 02/02/2023 | COT - FCON - Hood System - Final | Passed | ||
| 02/03/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 02/08/2023 | COT - FCON - Sprinkler - Final | Passed | ||
| 02/08/2023 | COT - FCON - Fire - Final | Passed | ||
| 02/21/2023 | COT - LCBU - Building Final | Passed | ok to issue C of O. | |
| 02/21/2023 | COT - LCBU - Building Above Ceiling | Passed |