Permit: T22CM04140
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
8002 E JULIA ST
Address NEW:
8002 E JULIA ST
Apply Date:
06/02/2022
Applicant:
Description:
R - Rooftop installation of PV Solar System, 8.64 kw DC System size, 2 circuits, with new main panel
Permit Reviews
Permit Number - T22CM04140
Permit Status: Issued
Permit Description: R - Rooftop installation of PV Solar System, 8.64 kw DC System size, 2 circuits, with new main panel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/02/2022 | OTHER | 07/26/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM04140
Permit Status: Issued
Permit Description: R - Rooftop installation of PV Solar System, 8.64 kw DC System size, 2 circuits, with new main panel
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/25/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T22CM04140
Permit Status: Issued
Permit Description: R - Rooftop installation of PV Solar System, 8.64 kw DC System size, 2 circuits, with new main panel
| Date | Description | Comments |
|---|---|---|
| 06/02/2022 | THE INSTALLATION SHALL COMPLY WITH ALL APPLICABLE REQUIREMENTS OF SECTION 605.11.1 THROUGH 605.11.4 OF THE 2012 EDITION OF THE INTERNATIONAL FIRE CODE, THE INTERNATIONAL BUILDING CODE AND NFPA 70. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM04140
Permit Description: R - Rooftop installation of PV Solar System, 8.64 kw DC System size, 2 circuits, with new main panel
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE INCR/CUTOVER} | |
| 08/25/2022 | COT - RSEL - Service Upgrade | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Need cutover for final Clear incr for cutover and solar} ; {Activity date: 08/22/2022; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by VVERA1 - nr Per Jesse} |
|
| 03/01/2023 | RSBU - Building Final | Passed | ||
| 03/01/2023 | COT - RSEL - Electrical Final | Passed | ||
| 03/01/2023 | BULD - Electrical Clearance | Passed | Approved, DGC Clearance is required to TEP for solar meter |