Permit: T22CM03977
Permit Details
Apply Date:
05/24/2022
Applicant:
Chris Vasquez
Description:
Toilet Addition
Permit Reviews
Permit Number - T22CM03977
Permit Status: In review
Permit Description: Toilet Addition
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/24/2022 | COMMERCIAL - TI | 07/01/2022 | COMPLETED |
07/06/2022 | RESUBMITTAL | 07/22/2022 | COMPLETED |
12/12/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/17/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM03977
Permit Status: In review
Permit Description: Toilet Addition
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
01/18/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
06/30/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
06/30/2022 | SHOP DRAWINGS REQUIRED FOR PLYWOOD JOISTS. |
Outstanding Inspections
Permit Status: In Review
Permit Number: T22CM03977
Permite Description: Toilet Addition
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
01/31/2023 | COT - LCBU - Preslab | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Roof Nailing | N/A | Not Ready | |
01/31/2023 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
03/01/2023 | COT - LCBU - Exterior Clips/Sheathing | N/A | Partial Pass | West wall incomplete |
Completed Inspections
Permit Status: In Review
Permit Number: T22CM03977
Permit Description: Toilet Addition
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/31/2023 | COT - LCPL - Rough Soil | Passed | ||
02/07/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
02/22/2023 | COT - LCBU - Preslab | Passed | ||
03/01/2023 | COT - LCBU - Roof Nailing | Passed | ||
04/07/2023 | COT - LCPL - Plumbing Intermediate | Passed | Plumbing rough in is complete. Okay to insulate and sheet rock interior walls. Okay to wrap and lath exterior walls. | |
04/07/2023 | COT - LCME - Mechanical Intermediate | Passed | Mechanical rough in is complete. Okay to insulate and sheet rock interior walls. Okay to wrap and lath exterior walls. | |
04/07/2023 | COT - LCEL - Electrical Intermediate | Passed | Electrical rough in is complete. Okay to insulate and sheet rock interior walls. Okay to wrap and lath exterior walls. | |
05/09/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
05/09/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
05/09/2023 | COT - FCON - Sprinkler - Final | Passed | building 12 | |
05/09/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
05/09/2023 | COT - FCON - Fire - Final | Passed | building 12 | |
05/09/2023 | COT - LCBU - Framing | Passed | ||
05/09/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
05/09/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
05/09/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
05/09/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
06/20/2023 | COT - LCBU - Building Final | Passed | ||
06/20/2023 | COT - LCEL - Electrical Final | Passed | ||
06/20/2023 | COT - LCPL - Plumbing Final | Passed | ||
06/20/2023 | COT - LCME - Mechanical Final | Passed |