Permit: T22CM03799
Permit Details
Apply Date:
05/18/2022
Applicant:
Description:
TI: RETAIL
Permit Reviews
Permit Number - T22CM03799
Permit Status: Issued
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/18/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/07/2022 | COMPLETED |
| 07/20/2022 | RESUBMITTAL | 08/10/2022 | COMPLETED |
| 08/16/2022 | RESUBMITTAL | 08/24/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM03799
Permit Status: Issued
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 08/01/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 08/01/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 08/01/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. |
Conditions
Permit Number - T22CM03799
Permit Status: Issued
Permit Description: TI: RETAIL
| Date | Description | Comments |
|---|---|---|
| 08/24/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM03799
Permite Description: TI: RETAIL
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
| 11/14/2022 | COT - LCME - Mechanical Final | N/A | Partial Pass | pending chlorination report |
| 10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03799
Permit Description: TI: RETAIL
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP. Underground in the parking lot.} ; {Activity date: 09/02/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Partial Approval: Walls only.} | |
| 10/11/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/11/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/11/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP SWG clearance.} | |
| 10/11/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/11/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/11/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE GAS} | |
| 10/12/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } | |
| 10/18/2022 | COT - LCBU - Building Final | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 10/18/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 01/12/2023 | COT - FCON - Fire - Final | Passed | ||
| 11/14/2022 | COT - LCPL - Gas Pressure Test | Passed | ||
| 11/14/2022 | COT - LCBU - Framing | Passed | ||
| 11/14/2022 | COT - LCPL - Plumbing Progress | Passed | ||
| 11/14/2022 | COT - LCME - Mechanical Progress | Passed | ||
| 11/14/2022 | COT - FCON - Alarm - Final | Passed | This was approved by fordney | |
| 11/14/2022 | COT - LCEL - Electrical Final | Passed | ||
| 11/14/2022 | COT - LCPL - Plumbing Final | Passed | ||
| 11/14/2022 | COT - HCBU - Interior Shear Bracing | Passed |