Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM03784
Permit Details
Apply Date:
05/18/2022
Applicant:
Richard Fifer
Description:
TI: Gentle Ben's
Permit Reviews
Permit Number - T22CM03784
Permit Status: Issued
Permit Description: TI: Gentle Ben's
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/18/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/20/2022 | COMPLETED |
09/08/2022 | REVISION - - 1ST | 09/08/2022 | ACTIVE |
10/27/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/28/2022 | APPROVED |
01/16/2024 | RESTAMP - COMMERCIAL v.1 | 01/17/2024 | APPROVED |
12/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/16/2024 | APPROVED |
09/08/2023 | RESTAMP - COMMERCIAL v.1 | 09/11/2023 | APPROVED |
08/31/2023 | COMMERCIAL REVIEW - FULL v.2 | 09/08/2023 | APPROVED |
05/19/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/20/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T22CM03784
Permit Status: Issued
Permit Description: TI: Gentle Ben's
Total Outstanding Activity Conditions - 8
Date | Name |
---|---|
07/20/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
07/20/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
07/20/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
07/20/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
07/20/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
07/20/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
07/20/2022 | SHOP DRAWINGS REQUIRED FOR AUTOMATIC FIRE SPRINKLERS. |
07/20/2022 | SHOP DRAWINGS REQUIRED FOR HOOD SUPPRESSION SYSTEM. |
Conditions
Permit Number - T22CM03784
Permit Status: Issued
Permit Description: TI: Gentle Ben's
Date | Description | Comments |
---|---|---|
12/28/2022 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM03784
Permite Description: TI: Gentle Ben's
Total Outstanding Inspections - 13
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Hood System - Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
09/22/2023 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Exhaust fan platform foundation plan, rebar per plan. Okay for concrete placement. 9/22/2023 |
07/10/2024 | COT - LCME - Kitchen Hood | N/A | Partial Pass | Hood duct system; smoke tested. Ok to wrap duct system and install. |
03/18/2024 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | Information only for scheduled power kill and application of new 200 amp panel: power kill to be scheduled for 21 March at 0300 hours. |
10/16/2024 | COT - FCON - Sprinkler - Final | N/A | Re-inspection required | Sprinkler head in front of the hood on north end needs to be clipped(braced). |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03784
Permit Description: TI: Gentle Ben's
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/21/2024 | BULD - Electrical Clearance | Passed | Verbal clearance to TEP INCR. 3/21/2024 | |
03/18/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
06/21/2024 | COT - LCBU - Framing | Passed | OK to hang kitchen hood. | |
06/21/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
10/03/2024 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
10/03/2024 | COT - LCME - Mechanical Final | Passed | ||
10/03/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
10/03/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
10/03/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
10/03/2024 | COT - LCEL - Electrical Final | Passed | ||
10/17/2024 | COT - FCON - Sprinkler - Final | Passed |