Permit: T22CM03746
Permit Details
Apply Date:
05/17/2022
Applicant:
Technicians for Sustainability
Description:
R - roof mount 8.40 kW DC photovoltaic solar system; 20 AC modules, 3 branches, 2 PV subpanels, 40A PV breaker on 200A bus with 200A MCB, trenching
Contractors:
- Technicians for Sustainability
Permit Reviews
Permit Number - T22CM03746
Permit Status: Final
Permit Description: R - roof mount 8.40 kW DC photovoltaic solar system; 20 AC modules, 3 branches, 2 PV subpanels, 40A PV breaker on 200A bus with 200A MCB, trenching
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/17/2022 | OTHER | 07/18/2022 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T22CM03746
Permit Description: R - roof mount 8.40 kW DC photovoltaic solar system; 20 AC modules, 3 branches, 2 PV subpanels, 40A PV breaker on 200A bus with 200A MCB, trenching
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE DGC/UNIT B |
| 10/19/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap Clear dgc #B Close permit |
| 10/19/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |