Apply Date:
05/13/2022
Applicant:
Christi Swenson
Description:
SFR PULT3519-3 T21-M0048
Outstanding Activity Conditions
Permit Number - T22CM03662
Permit Status: Issued
Permit Description: SFR PULT3519-3 T21-M0048
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
05/13/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
05/13/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
05/13/2022 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
05/24/2022 | SFR - ISSUED WITH PCRWRD CONDITIONS: NO FINAL UNTIL THE PUBLIC SEWER G-2020-089/P21WP00061 IS ACCEPTED AND RELEASED BY PCRWRD AND NO FINAL UNTIL THE DOWNSTREAM OFFSITE PUBLIC SEWER FOR PARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03662
Permit Description: SFR PULT3519-3 T21-M0048
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/27/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
06/27/2022 | COT - RSPL - Sewer | Passed | {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
06/27/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 06/27/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
07/07/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
07/07/2022 | COT - RSBU - Preslab | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
07/07/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
07/07/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/01/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
08/01/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
09/15/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
09/15/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 09/15/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
09/20/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/16/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready per previous notes} ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready per other notes. Missing nail plates on electrical lines} | |
09/20/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - CODE ECO} | |
09/20/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/16/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready per previous notes} ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready. Provide DWV test. Missing nail plates.} | |
09/20/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved. Clearance for TEP ECO. } ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready. Missing temporarily receptacle.} |
|
09/20/2022 | RSME - Mechanical Progress | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready. Missing blocking at register. Duct not tide into condenser unit.} | |
10/04/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 10/03/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready. Canceled per contractor.} ; {Activity date: 09/27/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Not ready. Walls incomplete. Still working in home.} | |
12/08/2022 | COT - BULD - SWG Clearance | Passed | clearance for Southwest Gas | |
02/27/2023 | COT - RSME - Mechanical Final | Passed | ||
02/27/2023 | RSBU - Building Final | Passed | ||
02/27/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
02/27/2023 | COT - RSPL - Plumbing Final | Passed | ||
02/27/2023 | COT - RSEL - Electrical Final | Passed |