Permit: T22CM03647
Permit Details
Apply Date:
05/12/2022
Applicant:
Description:
Tenant Improvement of 6,245 s.f. for a ASC in an existing building. Demo under separate permit (T22C
Permit Reviews
Permit Number - T22CM03647
Permit Status: Issued
Permit Description: Tenant Improvement of 6,245 s.f. for a ASC in an existing building. Demo under separate permit (T22C
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/13/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/28/2022 | COMPLETED |
| 07/07/2022 | RESUBMITTAL | 08/15/2022 | COMPLETED |
| 08/18/2022 | RESUBMITTAL | 09/06/2022 | COMPLETED |
| 09/13/2022 | RESUBMITTAL | 09/13/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM03647
Permit Status: Issued
Permit Description: Tenant Improvement of 6,245 s.f. for a ASC in an existing building. Demo under separate permit (T22C
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 08/27/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
| 08/27/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 08/27/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 08/27/2022 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 08/27/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 08/27/2022 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
| 08/27/2022 | SPECIAL INSPECTION FOR MEDICAL GASES IS REQUIRED. |
| 08/27/2022 | SHOP DRAWINGS REQUIRED FOR SPRINKLER. |
Conditions
Permit Number - T22CM03647
Permit Status: Issued
Permit Description: Tenant Improvement of 6,245 s.f. for a ASC in an existing building. Demo under separate permit (T22C
| Date | Description | Comments |
|---|---|---|
| 09/13/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM03647
Permite Description: Tenant Improvement of 6,245 s.f. for a ASC in an existing building. Demo under separate permit (T22C
Total Outstanding Inspections - 29
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
| 10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
| 10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - ENGR - Site - Assurance Release | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Service Upgrade | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Reconnect | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 09/29/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 9/29/23 partial approval for in/above ceiling ok for insulation |
| 10/06/2023 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Not Applicable | |
| 10/11/2023 | COT - LCPL - Gas Pressure Test | N/A | Not Applicable | |
| 10/11/2023 | COT - LCPL - Gas Reconnect | N/A | Not Applicable | |
| 10/11/2023 | COT - LCEL - Electrical Underground | N/A | Partial Pass | Interior. |
| 10/19/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
| 10/25/2023 | COT - LCPL - Medical Gas/Test | N/A | Not Ready | |
| 10/24/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | 10/24/23 partial approval in wall only OK to one side |
| 01/08/2024 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | Partial pass. All hard duct okay for first layer. Pending flex duct and hard lid rooms. 1/8/2023 |
| 12/11/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | 12/11/2023 new 2 front entry canopy. Okay to proceed progress areas. |
| 12/11/2023 | COT - LCBU - Roof Nailing | N/A | Partial Pass | 12/11/2023 new 2 front entry canopy. Okay to proceed progress areas. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03647
Permit Description: Tenant Improvement of 6,245 s.f. for a ASC in an existing building. Demo under separate permit (T22C
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2023 | COT - LCPL - Rough Soil | Passed | ||
| 07/20/2023 | COT - LCBU - Preslab | Passed | ||
| 10/19/2023 | COT - LCBU - Framing | Passed | ||
| 10/19/2023 | COT - LCPL - Plumbing Progress | Passed | ||
| 10/19/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 11/20/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 01/08/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 03/18/2024 | COT - LCBU - Building Progress | Passed | ||
| 03/18/2024 | COT - LCBU - Roof Nailing | Passed |