Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
4555 S MISSION RD
Apply Date:
05/10/2022
Applicant:
Description:
Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area

Permit Reviews

Permit Number - T22CM03587
Permit Status: Complete
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Start Date Submittal Complete Date Status  
05/10/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 06/21/2022 COMPLETED Review Details
07/21/2022 RESUBMITTAL 08/15/2022 COMPLETED Review Details

Conditions

Permit Number - T22CM03587
Permit Status: Complete
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Date Description Comments
07/25/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
07/25/2022 SHOP DRAWINGS REQUIRED FOR SIGNAGE.
07/25/2022 SHOP DRAWINGS REQUIRED FOR JOISTS.
07/25/2022 SHOP DRAWINGS REQUIRED FOR CURTAIN WALLS.
07/25/2022 SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION.
08/15/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM03587
Permite Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Total Outstanding Inspections - 11
Last Inspection Date Description Inspector Results Comments
10/03/2022 COT - LCME - Mechanical Progress N/A Canceled {Activity date: 10/03/2022; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by VVERA1 - NA}
10/27/2022 COT - LCEL - Electrical Final N/A Not Ready
10/26/2022 COT - LCEL - Electrical Progress N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Progress N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 COT - LCBU - Building Progress N/A Not Ready
10/26/2022 COT - LCEL - Electrical Intermediate N/A Not Ready
11/01/2022 COT - LCPL - Plumbing Intermediate N/A Partial Pass Partial for underground water and sewer lines to the outdoor kitchen, okay to backfill progress areas
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning N/A Not Ready
03/14/2023 BULD - Electrical Clearance N/A Not Applicable Duplicate
03/14/2023 COT - BULD - SWG Clearance N/A Not Applicable Duplicate

Completed Inspections

Permit Status: Complete
Permit Number: T22CM03587
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Total Completed Inspections - 12
Date Description Inspector Results Comments
10/03/2022 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved existing}
10/03/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved existing}
10/19/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to cover}
12/09/2022 COT - LCEL - Electrical Intermediate Passed
12/09/2022 COT - LCPL - Gas Pressure Test Passed
12/09/2022 COT - LCEL - Electrical Underground Passed
12/09/2022 COT - LCPL - Plumbing Intermediate Passed
12/09/2022 COT - LCEL - Service Upgrade Passed
03/14/2023 COT - FCON - Fire - Final Passed
03/14/2023 COT - LCPL - Plumbing Final Passed Previously approved
03/14/2023 COT - LCBU - Building Final Passed Approved, recommend C of O, pending Fire approvals
03/14/2023 COT - LCBU - Excavation/Rebar/Zoning Passed Previously approved