Permit: T22CM03587
Permit Details
Apply Date:
05/10/2022
Applicant:
Jason Kosmicki
Description:
Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Permit Reviews
Permit Number - T22CM03587
Permit Status: Complete
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/10/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/21/2022 | COMPLETED |
07/21/2022 | RESUBMITTAL | 08/15/2022 | COMPLETED |
Conditions
Permit Number - T22CM03587
Permit Status: Complete
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Date | Description | Comments |
---|---|---|
07/25/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
07/25/2022 | SHOP DRAWINGS REQUIRED FOR SIGNAGE. | |
07/25/2022 | SHOP DRAWINGS REQUIRED FOR JOISTS. | |
07/25/2022 | SHOP DRAWINGS REQUIRED FOR CURTAIN WALLS. | |
07/25/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
08/15/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03587
Permite Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2022 | COT - LCME - Mechanical Progress | N/A | Canceled | {Activity date: 10/03/2022; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by VVERA1 - NA} |
10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
11/01/2022 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | Partial for underground water and sewer lines to the outdoor kitchen, okay to backfill progress areas |
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
03/14/2023 | BULD - Electrical Clearance | N/A | Not Applicable | Duplicate |
03/14/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | Duplicate |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03587
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved existing} | |
10/03/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved existing} | |
10/19/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to cover} | |
12/09/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
12/09/2022 | COT - LCPL - Gas Pressure Test | Passed | ||
12/09/2022 | COT - LCEL - Electrical Underground | Passed | ||
12/09/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/09/2022 | COT - LCEL - Service Upgrade | Passed | ||
03/14/2023 | COT - FCON - Fire - Final | Passed | ||
03/14/2023 | COT - LCPL - Plumbing Final | Passed | Previously approved | |
03/14/2023 | COT - LCBU - Building Final | Passed | Approved, recommend C of O, pending Fire approvals | |
03/14/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Previously approved |