Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM03587
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
4555 S MISSION RD
Address NEW:
4555 S MISSION RD
Apply Date:
05/10/2022
Applicant:
Description:
Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Permit Reviews
Permit Number - T22CM03587
Permit Status: Complete
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/10/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/21/2022 | COMPLETED |
| 07/21/2022 | RESUBMITTAL | 08/15/2022 | COMPLETED |
Conditions
Permit Number - T22CM03587
Permit Status: Complete
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
| Date | Description | Comments |
|---|---|---|
| 07/25/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 07/25/2022 | SHOP DRAWINGS REQUIRED FOR SIGNAGE. | |
| 07/25/2022 | SHOP DRAWINGS REQUIRED FOR JOISTS. | |
| 07/25/2022 | SHOP DRAWINGS REQUIRED FOR CURTAIN WALLS. | |
| 07/25/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
| 08/15/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03587
Permite Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2022 | COT - LCME - Mechanical Progress | N/A | Canceled | {Activity date: 10/03/2022; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by VVERA1 - NA} |
| 10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
| 11/01/2022 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | Partial for underground water and sewer lines to the outdoor kitchen, okay to backfill progress areas |
| 10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| 03/14/2023 | BULD - Electrical Clearance | N/A | Not Applicable | Duplicate |
| 03/14/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | Duplicate |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03587
Permit Description: Front entry and Courtyard improvements and lobby renovations. Recommend TCO for office only. Please secure safe access and exiting of office area
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved existing} | |
| 10/03/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved existing} | |
| 10/19/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to cover} | |
| 12/09/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
| 12/09/2022 | COT - LCPL - Gas Pressure Test | Passed | ||
| 12/09/2022 | COT - LCEL - Electrical Underground | Passed | ||
| 12/09/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 12/09/2022 | COT - LCEL - Service Upgrade | Passed | ||
| 03/14/2023 | COT - FCON - Fire - Final | Passed | ||
| 03/14/2023 | COT - LCPL - Plumbing Final | Passed | Previously approved | |
| 03/14/2023 | COT - LCBU - Building Final | Passed | Approved, recommend C of O, pending Fire approvals | |
| 03/14/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Previously approved |