Permit: T22CM03549
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1209 W SONORA ST 2
Address NEW:
1209 W SONORA ST 2
Apply Date:
05/10/2022
Applicant:
FRANK MORENO
Description:
Secondary dwelling unit
Permit Reviews
Permit Number - T22CM03549
Permit Status: Issued
Permit Description: Secondary dwelling unit
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/10/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/02/2022 | COMPLETED |
| 06/08/2022 | RESUBMITTAL | 07/11/2022 | COMPLETED |
| 07/18/2022 | RESUBMITTAL | 07/19/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM03549
Permit Status: Issued
Permit Description: Secondary dwelling unit
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 07/19/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm |
| 07/19/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM03549
Permite Description: Secondary dwelling unit
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03549
Permit Description: Secondary dwelling unit
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/22/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/22/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover progress area. } |
|
| 07/27/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 07/27/2022 | COT - RSBU - Preslab | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 07/27/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 09/02/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to dry in roof system.} | |
| 09/02/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 09/02/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to cover exterior walls.} | |
| 10/04/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 10/03/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 06/14/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } | |
| 10/04/2022 | RSME - Mechanical Progress | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 10/03/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 06/14/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } | |
| 10/04/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
| 10/07/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/04/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready. Provide fire foam at all top penetrations.} | |
| 10/07/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/04/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready. Missing peninsular in kitchen area.} | |
| 10/19/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover progress areas. } |
|
| 12/23/2022 | COT - RSPL - Sewer | Passed | ||
| 01/23/2023 | COT - RSPL - Yard Water Line | Passed | Ok,to cover progress areas. | |
| 02/13/2023 | RSBU - Building Final | Passed | Gas service to be connected to service at building #1, one meter to serve both buildings. | |
| 02/17/2023 | COT - RSEL - Construction Power | Passed | ||
| 02/17/2023 | COT - RSEL - Electrical Final | Passed | ||
| 02/17/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 02/17/2023 | COT - RSME - Mechanical Final | Passed | ||
| 02/17/2023 | COT - RSPL - Plumbing Final | Passed |