Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM03401
Permit Details
Apply Date:
05/04/2022
Applicant:
burak bekat
Description:
SFR BRIO1432 T20-M0058
Permit Reviews
Permit Number - T22CM03401
Permit Status: Complete
Permit Description: SFR BRIO1432 T20-M0058
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/04/2022 | OTHER | 06/08/2022 | COMPLETED |
02/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/05/2024 | APPROVED |
02/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/06/2024 | APPROVED |
Conditions
Permit Number - T22CM03401
Permit Status: Complete
Permit Description: SFR BRIO1432 T20-M0058
Date | Description | Comments |
---|---|---|
05/04/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
05/04/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
05/04/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
05/04/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
05/04/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
05/04/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
05/04/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
05/19/2022 | WATER METER SIZE |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03401
Permite Description: SFR BRIO1432 T20-M0058
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/24/2023 | COT - LCPL - Plumbing Intermediate | N/A | Re-inspection required | |
04/24/2023 | RSME - Mechanical Progress | N/A | Re-inspection required | 4-24-23: 1-Block vent on 3 sides in hall and bedroom. |
11/27/2023 | COT - RSEL - Construction Power | N/A | Not Applicable | |
11/27/2023 | COT - RSBU - Sustainability | N/A | Not Applicable | |
04/24/2023 | COT - LCBU - Framing | N/A | Re-inspection required | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
11/27/2023 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03401
Permit Description: SFR BRIO1432 T20-M0058
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/05/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/05/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/04/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Contractor cancelled; will reschedule for 5 October.} | |
10/17/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
10/17/2022 | COT - RSBU - Preslab | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
10/17/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
11/04/2022 | COT - RSBU - Roof Nailing | Passed | ||
04/24/2023 | RSEL - Electrical Progress | Passed | ||
04/25/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
04/25/2023 | RSME - Mechanical Progress | Passed | ||
05/02/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
10/03/2023 | BULD - Electrical Clearance | Passed | 10/3/23 Clearance ECO | |
11/27/2023 | COT - RSPL - Yard Water Line | Passed | ||
11/27/2023 | COT - RSEL - Electrical Underground | Passed | ||
11/27/2023 | COT - LCBU - Framing | Passed | ||
11/27/2023 | COT - RSPL - Plumbing Final | Passed | ||
11/27/2023 | COT - RSEL - Electrical Final | Passed | ||
11/27/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/27/2023 | COT - RSME - Mechanical Final | Passed | ||
11/27/2023 | COT - RSPL - Sewer | Passed | ||
01/04/2024 | COT - FCON - Fire - Final | Passed | ||
02/12/2024 | ENGR Engineering Final | Passed | ||
02/21/2024 | RSBU - Building Final | Passed | Ok for CofO |