Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
04/29/2022
Applicant:
Description:
SFR 230.2690 T21-M0027

Outstanding Activity Conditions

Permit Number - T22CM03253
Permit Status: Issued
Permit Description: SFR 230.2690 T21-M0027
Total Outstanding Activity Conditions - 4
Date Name
04/29/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
04/29/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
04/29/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/29/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-100/P21WP00059, G-20-059/P20WP00060, G-20-089/P20WP00061 AND THE DOWNSTREAM OFFSITEPUBLIC SEWER FOR PARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM03253
Permite Description: SFR 230.2690 T21-M0027
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
11/18/2022 COT - LCPL - Plumbing Intermediate N/A Not Ready per previous notes. tub is leaking downstairs bathroom.
10/27/2022 RSME - Mechanical Progress N/A Not Ready
04/21/2023 COT - RSME - Mechanical Final N/A Partial Pass 4/21/23. Condensate line is too close to the ground. Indicate what heat strip is being used in the furnace.
04/21/2023 COT - RSEL - Electrical Final N/A Partial Pass 4/21/23. Unable to access shutoff furnace switch

Completed Inspections

Permit Status: Issued
Permit Number: T22CM03253
Permit Description: SFR 230.2690 T21-M0027
Total Completed Inspections - 23
Date Description Inspector Results Comments
06/17/2022 COT - RSPL - Sewer Passed {Activity date: 06/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
06/17/2022 COT - RSPL - Rough Soil Passed {Activity date: 06/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
06/29/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 06/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/29/2022 COT - RSBU - Preslab Passed {Activity date: 06/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/29/2022 COT - RSEL - Electrical Underground Passed {Activity date: 06/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
06/29/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 06/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
08/01/2022 COT - RSBU - Roof Nailing Passed {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/29/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} ; {Activity date: 07/27/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by RSALDAT1 - not ready. Provide ladder.}
08/01/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/29/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} ; {Activity date: 07/27/2022; Status: Denied; Inspector: SCARRAZCO; Comment: Entered by RSALDAT1 - denied. Missing too many nails on upstairs perimeter exterior wall.}
11/15/2022 COT - RSPL - Yard Water Line Passed
11/15/2022 COT - RSEL - Construction Power Passed clearance for TEP ECO.
11/15/2022 COT - RSPL - Gas Pressure Test Passed
11/18/2022 COT - LCBU - Framing Passed corrections were made.
11/18/2022 BULD - Electrical Clearance Passed
11/23/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed corrections were made
11/23/2022 COT - LCPL - Plumbing Intermediate Passed
11/23/2022 RSME - Mechanical Progress Passed
01/10/2023 COT - HCBU - Interior Shear Bracing Passed
04/06/2023 COT - BULD - SWG Clearance Passed SWG for meter only
04/21/2023 COT - RSPL - Plumbing Final Passed
04/21/2023 RSBU - Building Final Passed Pass
04/21/2023 COT - RSEL - Outdoor Lighting Passed pass
04/25/2023 COT - RSME - Mechanical Final Passed
04/25/2023 COT - RSEL - Electrical Final Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SITE PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW