Permit: T22CM03185
Permit Details
Apply Date:
04/28/2022
Applicant:
burak bekat
Description:
SFR BRIO1432 T20-M0058
Permit Reviews
Permit Number - T22CM03185
Permit Status: Complete
Permit Description: SFR BRIO1432 T20-M0058
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/28/2022 | OTHER | 06/08/2022 | COMPLETED |
02/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/05/2024 | APPROVED |
02/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/06/2024 | APPROVED |
Conditions
Permit Number - T22CM03185
Permit Status: Complete
Permit Description: SFR BRIO1432 T20-M0058
Date | Description | Comments |
---|---|---|
04/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
05/10/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
05/10/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
05/10/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
05/10/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
05/10/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
05/10/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
05/12/2022 | WATER METER SIZE |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03185
Permite Description: SFR BRIO1432 T20-M0058
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - RSEL - Electrical Underground | N/A | Not Ready | |
12/11/2023 | COT - RSEL - Construction Power | N/A | Not Applicable | |
12/11/2023 | COT - RSBU - Sustainability | N/A | Not Applicable | |
12/11/2023 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 12/11/23: UV coat all exterior piping on roof, water heater leaking |
12/11/2023 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | |
12/11/2023 | RSBU - Building Final | N/A | Re-inspection required | 12/11/23: UV coat all exterior piping on roof, water heater leaking |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03185
Permit Description: SFR BRIO1432 T20-M0058
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/08/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Inspection canceled by contractor } |
|
08/29/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
08/29/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
08/29/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
09/21/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
02/15/2023 | COT - RSEL - Electrical Underground | Passed | ||
02/15/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
02/15/2023 | RSEL - Electrical Progress | Passed | ||
02/15/2023 | RSME - Mechanical Progress | Passed | ||
02/16/2023 | COT - LCBU - Framing | Passed | ||
02/16/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
03/17/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
09/07/2023 | BULD - Electrical Clearance | Passed | ||
12/11/2023 | COT - RSPL - Yard Water Line | Passed | ||
12/11/2023 | COT - RSPL - Sewer | Passed | ||
12/11/2023 | COT - RSEL - Electrical Final | Passed | ||
12/29/2023 | COT - RSME - Mechanical Final | Passed | ||
12/29/2023 | COT - RSPL - Plumbing Final | Passed | ||
02/12/2024 | ENGR Engineering Final | Passed | ||
02/20/2024 | RSBU - Building Final | Passed | OK for CofO |