Permit: T22CM02977
Permit Details
Apply Date:
04/21/2022
Applicant:
joe oneill
Description:
Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Permit Reviews
Permit Number - T22CM02977
Permit Status: Issued
Permit Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/21/2022 | COMMERCIAL - NEW | 05/31/2022 | COMPLETED |
03/16/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/24/2023 | REQUIRES RESUBMIT |
05/09/2023 | COMMERCIAL REVIEW - FULL v.3 | 06/12/2023 | APPROVED |
06/12/2023 | ZZZBUILDING RESTAMP REVIEW v.1 | 06/18/2023 | APPROVED |
03/16/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/16/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T22CM02977
Permit Status: Issued
Permit Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Total Outstanding Activity Conditions - 14
Date | Name |
---|---|
05/02/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
05/02/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
05/02/2022 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
05/02/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
05/02/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
05/02/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
05/02/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/02/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
05/16/2022 | Special inspection for outside lighting |
06/12/2023 | AIR BALANCING REPORT IS REQUIRED. |
06/12/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
06/12/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
06/18/2023 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. |
06/18/2023 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM02977
Permite Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/20/2024 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | 8/29/24: 3" PVC schedule 40 from ball valve to P.O.C at existing restrooms. Ok to backfill progress area. Shading required 9/20/24: not ready |
08/14/2024 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 8/8/24: (1)1" for circuit HA-1 at north east entrance 50' stretch, (1)4" conduit for primary feeders from utility pole to future stub up of transformer, (1)2" for communication from utility pole to building 80', (2)3" for secondaries from future stub up at transformer to SES (100'), ok to backfill progress areas, 8/14/24: partial electrical underground for East/West trench, LB panel at concession building, panel LC under restroom building, trench across north parking lot, |
08/08/2024 | COT - LCPL - Sewer | N/A | Partial Pass | 6/18/24: Pre con meeting 7/23/24: Canceled by Joel. 7/31/24: Sewer tie in passed, 4" partial pass from sewer tie in at north east corner of project to second clean-out on north east side of project. Ok to backfill progress areas. Shading required. Air test will be conducted at future inspection, 8/8/24: air test passed. Ok to proceed |
10/15/2024 | COT - LCBU - Building Progress | N/A | Partial Pass | 10-15-24, first lift at 4' for concession stand and bathroom per approved plans. Okay to proceed. |
10/23/2024 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout. |
10/23/2024 | COT - LCBU - Preslab | N/A | Partial Pass | 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout. |
10/23/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout. |
12/23/2024 | COT - LCBU - Masonry Pregrout | N/A | Partial Pass | 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout. 12/23: reinforcement per plan at column north of bathrooms. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM02977
Permit Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/02/2024 | COT - LCEL - Electrical Underground | Passed | ||
10/02/2024 | COT - LCPL - Rough Soil | Passed | ||
10/02/2024 | COT - LCPL - Yard Water Line | Passed | ||
10/02/2024 | COT - LCPL - Sewer | Passed |