Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
3700 S MISSION RD
Apply Date:
04/21/2022
Applicant:
joe oneill
Description:
Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se

Permit Reviews

Permit Number - T22CM02977
Permit Status: Complete
Permit Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Start Date Submittal Complete Date Status  
04/21/2022 COMMERCIAL - NEW 05/31/2022 COMPLETED Review Details
03/16/2023 COMMERCIAL REVIEW - FULL v.2 04/24/2023 REQUIRES RESUBMIT Review Details
09/22/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/24/2025 REQUIRES RESUBMIT Review Details
10/22/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 10/23/2025 APPROVED Review Details
05/09/2023 COMMERCIAL REVIEW - FULL v.3 06/12/2023 APPROVED Review Details
06/12/2023 ZZZBUILDING RESTAMP REVIEW v.1 06/18/2023 APPROVED Review Details
03/16/2023 COMMERCIAL REVIEW - FULL v.1 03/16/2023 REQUIRES RESUBMIT Review Details
10/31/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/04/2025 APPROVED Review Details

Conditions

Permit Number - T22CM02977
Permit Status: Complete
Permit Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Date Description Comments
06/12/2023 AIR BALANCING REPORT IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
05/02/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
05/02/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
06/12/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
06/18/2023 Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit.
06/18/2023 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
06/12/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM02977
Permite Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
08/14/2024 COT - LCEL - Electrical Underground N/A Partial Pass 8/8/24: (1)1" for circuit HA-1 at north east entrance 50' stretch, (1)4" conduit for primary feeders from utility pole to future stub up of transformer, (1)2" for communication from utility pole to building 80', (2)3" for secondaries from future stub up at transformer to SES (100'), ok to backfill progress areas,
8/14/24: partial electrical underground for East/West trench, LB panel at concession building, panel LC under restroom building, trench across north parking lot,
08/08/2024 COT - LCPL - Sewer N/A Partial Pass 6/18/24: Pre con meeting
7/23/24: Canceled by Joel.
7/31/24: Sewer tie in passed, 4" partial pass from sewer tie in at north east corner of project to second clean-out on north east side of project. Ok to backfill progress areas. Shading required. Air test will be conducted at future inspection,
8/8/24: air test passed. Ok to proceed
12/23/2024 COT - LCBU - Masonry Pregrout N/A Partial Pass 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout.
12/23: reinforcement per plan at column north of bathrooms.
10/23/2024 COT - LCEL - Grounding/Bonding N/A Partial Pass 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout.
10/23/2024 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout.
10/15/2024 COT - LCBU - Building Progress N/A Partial Pass 10-15-24, first lift at 4' for concession stand and bathroom per approved plans. Okay to proceed.
10/23/2024 COT - LCBU - Preslab N/A Partial Pass 10/23/24: reinforcement per plan at concession stand and bathrooms 2nd lift/ top out ok to proceed with grout.
04/21/2025 BULD - Electrical Clearance N/A Not Ready Grounding electrode conductor not per code for 400amp service. Provide #2 ground. 4/21/2025
05/09/2025 COT - LCBU - Roof Nailing N/A Re-inspection required 5-9-25, submit a letter to the city for review and approval regarding any framing, nailing/screws/bolts, insulation, etc.. which was covered without inspection. The letter must indicate that framing was installed according to approved plans and meets the 2018 International Code.
Note: See pending conditions.
05/09/2025 COT - LCBU - Framing N/A Re-inspection required 5-9-25, submit a letter to the city for review and approval regarding any framing, screws/bolts, insulation, etc.. which was covered without inspection. The letter must indicate that framing was installed according to approved plans and meets the 2018 International Code.
Note: See pending conditions.
05/09/2025 COT - LCME - Mechanical Intermediate N/A Partial Pass 5-9-25, partial pass-construction is continuous and is not quite complete.
02/25/2025 COT - LCPL - Plumbing Intermediate N/A Partial Pass 2-25-25, plumbing intermediate at concession stand/bathrooms verified under test and per approved plans. Okay to continue with construction.
08/29/2025 COT - FCON - Fire - Final N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: T22CM02977
Permit Description: Construction of 3 baseball fields, new restroom, walking paths & associated parking (DP submitted se
Total Completed Inspections - 21
Date Description Inspector Results Comments
10/02/2024 COT - LCEL - Electrical Underground Passed
10/02/2024 COT - LCPL - Rough Soil Passed
10/02/2024 COT - LCPL - Yard Water Line Passed
10/02/2024 COT - LCPL - Sewer Passed
05/09/2025 COT - LCBU - Masonry Pregrout Passed 5-9-25, masonry pre grout previously inspected and approved.
05/09/2025 COT - LCEL - Grounding/Bonding Passed 5-9-25, grounding/bonding verified as per approved plans.
05/09/2025 COT - LCEL - Electrical Intermediate Passed 5-9-25, electrical intermediate inspection approved.
05/09/2025 COT - LCBU - Excavation/Rebar/Zoning Passed 5-9-25 excavation/reinforcement approved.
05/09/2025 COT - LCBU - Building Progress Passed 5-9-25, building progress approved.
05/09/2025 COT - LCBU - Preslab Passed 5-9-25, preslab approved.
06/04/2025 BULD - Electrical Clearance Passed Clearance for TEP RECN. (Faulty breaker replacement). 6/4/2025
06/23/2025 COT - LCBU - Roof Nailing Passed
06/23/2025 COT - LCBU - Framing Passed
06/23/2025 COT - LCME - Mechanical Intermediate Passed
06/23/2025 COT - LCEL - Electrical Final Passed
06/30/2025 COT - LCPL - Plumbing Final Passed
06/30/2025 COT - LCME - Mechanical Final Passed
06/30/2025 COT - LCPL - Plumbing Intermediate Passed
07/10/2025 COT - HCEL - Outdoor Lighting Passed
08/29/2025 COT - LCBU - Building Final Passed 7-29-25: Building final approved.
Note: see pending conditions.
09/02/2025 ENGR Engineering Final Passed Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
T22CM02977_SPECIAL_INSPECTION_CERTIFICATE_ODL_V1.PDF DOCUMENTS VIEW
TDC CONDITIONS-2025-10-22_V2.PDF DOCUMENTS VIEW
2_GEOTECH_V1.PDF DOCUMENTS VIEW
2_STRUCTURAL CALCULATIONS_V1.PDF DOCUMENTS VIEW
CONS-3_PLAN SET_V2.PDF DOCUMENTS VIEW
CONS-3_PLAN SET_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW