Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM02926
Permit Details
Apply Date:
04/20/2022
Applicant:
Lisa Bowers
Description:
New Restroom building (deferred submittal) with utility connections
Permit Reviews
Permit Number - T22CM02926
Permit Status: In revision
Permit Description: New Restroom building (deferred submittal) with utility connections
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/20/2022 | COMMERCIAL - NEW | 05/18/2022 | COMPLETED |
05/23/2022 | REVISION - - 1ST | 06/13/2022 | COMPLETED |
08/02/2022 | REVISION - - 1ST | 08/04/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM02926
Permit Status: In revision
Permit Description: New Restroom building (deferred submittal) with utility connections
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/04/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: In Revision
Permit Number: T22CM02926
Permite Description: New Restroom building (deferred submittal) with utility connections
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2022 | COT - LCEL - Electrical Intermediate | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by ESTEVEN1 - PRE-FAB BUILDING.} |
10/19/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by ESTEVEN1 - PRE-FAB BUILDING.} |
10/19/2022 | COT - LCEL - Grounding/Bonding | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by ESTEVEN1 - PRE-FAB BUILDING.} |
Completed Inspections
Permit Status: In Revision
Permit Number: T22CM02926
Permit Description: New Restroom building (deferred submittal) with utility connections
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2022 | COT - LCBU - Building Final | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/26/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE Underground utilities have not been inspected. Grout inspections have not been inspected. Framing connection to masonry wall not inspected} ; {Activity date: 09/23/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA Could not locate pre-fab restroom at site. No messages or number left. } ; {Activity date: 07/14/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA contractor and plans not on site} ; {Activity date: 07/14/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} |
|
10/19/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
10/19/2022 | COT - LCEL - Outdoor Lighting | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
10/19/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} |