Permit: T22CM02884
Permit Details
Apply Date:
04/19/2022
Applicant:
Description:
71.04kW DC Photovoltaic Solar Canopy Installation
Permit Reviews
Permit Number - T22CM02884
Permit Status: Complete
Permit Description: 71.04kW DC Photovoltaic Solar Canopy Installation
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/19/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/19/2022 | COMPLETED |
| 05/24/2022 | RESUBMITTAL | 05/31/2022 | COMPLETED |
| 01/09/2023 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 02/06/2023 | APPROVED |
Conditions
Permit Number - T22CM02884
Permit Status: Complete
Permit Description: 71.04kW DC Photovoltaic Solar Canopy Installation
| Date | Description | Comments |
|---|---|---|
| 05/03/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
| 05/03/2022 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
| 05/03/2022 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 05/03/2022 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02884
Permit Description: 71.04kW DC Photovoltaic Solar Canopy Installation
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/29/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | approved column footings | |
| 11/29/2022 | COT - LCBU - Preslab | Passed | approved column footings | |
| 11/29/2022 | COT - LCEL - Grounding/Bonding | Passed | 12’ columns into grade | |
| 12/01/2022 | COT - LCEL - Electrical Underground | Passed | Approved from gear rack to risers at solar structure, okay to backfill progress areas | |
| 12/13/2022 | COT - LCBU - Framing | Passed | ||
| 12/13/2022 | COT - LCBU - Building Progress | Passed | ||
| 12/13/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
| 12/16/2022 | BULD - Electrical Clearance | Passed | Approved, DGC clearance to TEP is required | |
| 12/16/2022 | COT - LCBU - Building Final | Passed | Solar structure | |
| 12/16/2022 | COT - LCEL - Electrical Final | Passed | Approved, DGC clearance to TEP is required | |
| 12/19/2022 | COT - LCEL - Outdoor Lighting | Passed |