Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
04/19/2022
Applicant:
Description:
SFR 130.1600 T21-M0030

Outstanding Activity Conditions

Permit Number - T22CM02873
Permit Status: Issued
Permit Description: SFR 130.1600 T21-M0030
Total Outstanding Activity Conditions - 4
Date Name
04/19/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
04/19/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
04/19/2022 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/19/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-100/P21WP00059, G-20-059/P20WP00060, G-20-089/P20WP00061 AND THE DOWNSTREAM OFFSITEPUBLIC SEWER FOR PARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM02873
Permite Description: SFR 130.1600 T21-M0030
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSEL - Grounding/Bonding N/A Not Ready
10/26/2022 COT - RSEL - Electrical Underground N/A Not Ready
10/26/2022 COT - RSBU - Preslab N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM02873
Permit Description: SFR 130.1600 T21-M0030
Total Completed Inspections - 23
Date Description Inspector Results Comments
05/26/2022 COT - RSPL - Sewer Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
05/26/2022 COT - RSPL - Rough Soil Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved}
06/14/2022 COT - RSPL - Yard Water Line Passed {Activity date: 06/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/26/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Not ready}
07/01/2022 COT - RSBU - Roof Nailing Passed {Activity date: 07/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
07/01/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 07/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
08/19/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO}
08/19/2022 COT - RSEL - Construction Power Passed {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP. TEP ECO}
08/19/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
08/19/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 08/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/08/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Inspection canceled by contractor

}
08/25/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 08/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 08/19/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE
1. Burn in line-set
2. Replace fresh air duct}
08/25/2022 COT - LCBU - Framing Passed {Activity date: 08/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
08/25/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 08/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
08/25/2022 RSME - Mechanical Progress Passed {Activity date: 08/25/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/22/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 09/22/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 09/21/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready. Missing dry wall screws above ceiling. Screws need to be 3/8 from edge.}
12/06/2022 COT - RSEL - Grounding/Bonding Passed
12/06/2022 COT - RSEL - Electrical Underground Passed
12/06/2022 COT - RSBU - Preslab Passed
12/21/2022 COT - BULD - SWG Clearance Passed
02/14/2023 COT - RSPL - Plumbing Final Passed
02/14/2023 COT - RSME - Mechanical Final Passed
02/14/2023 COT - RSEL - Outdoor Lighting Passed
02/21/2023 COT - RSEL - Electrical Final Passed
02/21/2023 RSBU - Building Final Passed

Documents

File Name Document Type  
JOB CARD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW