Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM02567
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3346 S 6TH AV UNIT 192
Address NEW:
3346 S 6TH AV UNIT 192
Apply Date:
04/07/2022
Applicant:
Chuck McDuffie
Description:
TI: Dental Office
Permit Reviews
Permit Number - T22CM02567
Permit Status: Complete
Permit Description: TI: Dental Office
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/07/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 07/14/2022 | COMPLETED |
| 09/07/2022 | RESUBMITTAL | 10/03/2022 | COMPLETED |
| 08/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/18/2023 | APPROVED |
| 12/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2023 | REQUIRES RESUBMIT |
| 12/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/19/2023 | APPROVED |
Conditions
Permit Number - T22CM02567
Permit Status: Complete
Permit Description: TI: Dental Office
| Date | Description | Comments |
|---|---|---|
| 07/14/2022 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM | |
| 10/03/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02567
Permite Description: TI: Dental Office
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Service Relocation | N/A | Not Ready | |
| 10/26/2022 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
| 05/31/2023 | COT - LCBU - Preslab | N/A | Not Ready | Not ready for inspection. Contractor wanted to keep permit open. |
| 11/14/2023 | COT - LCBU - Building Above Ceiling | N/A | Partial Pass | call with finals after ceiling tiles |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02567
Permit Description: TI: Dental Office
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/12/2023 | COT - LCPL - Rough Soil | Passed | Ok to cover progress areas. | |
| 06/15/2023 | COT - LCBU - Preslab | Passed | Ok to place concrete in progress areas. | |
| 06/15/2023 | COT - LCEL - Electrical Underground | Passed | Ok to cover electric in slab. | |
| 08/03/2023 | COT - LCPL - Medical Gas Preconstruction Mtg | Passed | third party inspection, in wall complete | |
| 09/18/2023 | COT - LCEL - Electrical Intermediate | Passed | partial approval for all areas in wall excluding rooms 141,142 and 143 9/18/23: Rooms 141, 142, 143 approved to proceed insulate and cover. |
|
| 09/18/2023 | COT - LCBU - Framing | Passed | partial approval for all areas in wall excluding rooms 141,142 and 143 9/18/23: Rooms 141, 142, 143 approved to proceed insulate and cover. |
|
| 09/18/2023 | COT - LCPL - Plumbing Intermediate | Passed | partial approval for all areas in wall excluding rooms 141,142 and 143 9/18/23: Rooms 141, 142, 143 approved to proceed insulate and cover. |
|
| 09/18/2023 | COT - LCME - Mechanical Intermediate | Passed | partial approval for all areas in wall excluding rooms 141,142 and 143 9/18/23: Rooms 141, 142, 143 approved to proceed insulate and cover. |
|
| 10/05/2023 | BULD - Electrical Clearance | Passed | Approved, ECO clearance to TEP is required for unit #192 meter #M3 | |
| 10/05/2023 | COT - LCEL - Service Upgrade | Passed | Approved, ECO clearance to TEP is required for unit #192 meter #M3 | |
| 11/14/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 11/14/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 11/14/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 11/22/2023 | COT - LCPL - Medical Gas/Test | Passed | ||
| 11/27/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 11/27/2023 | COT - LCME - Mechanical Final | Passed | ||
| 11/27/2023 | COT - LCBU - Building Final | Passed | 11/27/23: pending air balance report, sterilization report. | |
| 11/27/2023 | COT - LCEL - Electrical Final | Passed | ||
| 11/27/2023 | COT - FCON - Fire - Final | Passed | ||
| 02/01/2024 | COT - FCON - Sprinkler - Final | Passed | Passed VIA TF-FCP-1123-01323 |