Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Address:
704 E PRINCE RD
Address NEW:
704 E PRINCE RD
Apply Date:
04/01/2022
Applicant:
Andrew Venne
Description:
TI: MARKET

Permit Reviews

Permit Number - T22CM02430
Permit Status: Complete
Permit Description: TI: MARKET
Start Date Submittal Complete Date Status  
04/01/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 04/29/2022 COMPLETED Review Details
05/06/2022 RESUBMITTAL 05/11/2022 COMPLETED Review Details
04/09/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/15/2025 APPROVED Review Details
10/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/29/2025 APPROVED Review Details
10/25/2024 COMMERCIAL REVIEW - FULL v.1 11/19/2024 APPROVED Review Details
11/10/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/13/2025 APPROVED Review Details

Conditions

Permit Number - T22CM02430
Permit Status: Complete
Permit Description: TI: MARKET
Date Description Comments
11/10/2025 AIR BALANCING REPORT IS REQUIRED.
05/11/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
11/10/2025 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
11/10/2025 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM02430
Permite Description: TI: MARKET
Total Outstanding Inspections - 17
Last Inspection Date Description Inspector Results Comments
07/11/2023 COT - LCEL - Electrical Intermediate N/A Not Ready
08/16/2023 COT - LCPL - Plumbing Progress N/A Re-inspection required (with fee) 8/16/23: city approved plans not on site, the area inside this building is hazardous to walk around in. Clean up this construction site before anymore inspections. Pay a re-fee charge before next inspection.
05/31/2024 COT - BULD - SWG Clearance N/A Not Ready
10/26/2022 COT - HCBU - Interior Shear Bracing N/A Not Ready
10/26/2022 COT - LCBU - Building Above Ceiling N/A Not Ready
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/26/2022 COT - LCBU - Preslab N/A Not Ready
05/01/2023 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCME - Mechanical Above Ceiling N/A Not Ready
10/26/2022 COT - LCEL - Service Upgrade N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Intermediate N/A Not Ready
10/26/2022 COT - LCME - Mechanical Progress N/A Not Ready
03/11/2025 COT - LCPL - Plumbing Final N/A Canceled
08/16/2023 COT - LCPL - Plumbing Intermediate N/A Re-inspection required (with fee) 8/16/23: city approved plans not on site, the area inside this building is hazardous to walk around in. Clean up this construction site before anymore inspections. Pay a re-fee charge before next inspection.
10/26/2022 COT - LCBU - Building Progress N/A Not Ready
11/21/2022 COT - LCEL - Outdoor Lighting N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM02430
Permit Description: TI: MARKET
Total Completed Inspections - 21
Date Description Inspector Results Comments
06/24/2022 COT - LCPL - Rough Soil Passed {Activity date: 06/24/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap
All rough, including grease trap, ok to backfill.}
05/01/2023 BULD - Electrical Clearance Passed
07/28/2023 COT - LCEL - Electrical Intermediate Passed
03/18/2025 COT - BULD - SWG Clearance Passed
03/18/2025 COT - HCBU - Interior Shear Bracing Passed
04/08/2025 COT - LCEL - Electrical Final Passed 4-8-25, electrical final approved.
04/08/2025 COT - LCBU - Building Above Ceiling Passed 4-8-25, approved.
04/08/2025 COT - LCEL - Electrical Above Ceiling Passed 4-8-25, electrical above ceiling approved.
04/08/2025 COT - LCEL - Electrical Progress Passed 4-8-25, electrical above ceiling approved.
04/08/2025 COT - LCME - Mechanical Above Ceiling Passed 4-8-25, mechanical final approved.
04/08/2025 COT - LCME - Mechanical Final Passed 4-8-25, mechanical final approved.
04/08/2025 COT - LCME - Mechanical Intermediate Passed 4-8-25, approved.
04/08/2025 COT - LCME - Mechanical Progress Passed 4-8-25, approved
04/08/2025 COT - LCPL - Gas Pressure Test Passed 4-8-25, previously inspected & approved.
04/08/2025 COT - LCPL - Plumbing Final Passed 4-8-25, plumbing final approved.
04/08/2025 COT - LCBU - Building Progress Passed 4-8-25, approved.
04/08/2025 COT - LCEL - Outdoor Lighting Passed 4-8-25, approved.
04/29/2025 COT - FCON - Fire - Final Passed
10/30/2025 COT - LCME - Kitchen Hood Passed
10/30/2025 COT - FCON - Hood System - Final Passed Approved on 4/28/25 on permit # TF-FCP-0324-00244
10/30/2025 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
25D0032_1 TURNERRES 04 04 2025 1536-2025-04-07_V1.PDF DOCUMENTS VIEW
DONJUAN (1)_V1.PDF DOCUMENTS VIEW
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
MECH CHECK 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SYSTEMS DESIGN REPORT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
T22CM02430 PLAN REVIEW FEE AND INSPECTION SHEET 2024 MASS-UPLOAD.DOCX DOCUMENTS VIEW
1_DON JUAN 2 STRUCTURAL CALCULATIONS_V1.PDF DOCUMENTS VIEW
24269 SYSTEMS DESIGN REPORT_V1.PDF DOCUMENTS VIEW
COMMENT LETTER TO CITY OF TUCSON DON JUAN 10-24-24_V1.PDF DOCUMENTS VIEW
CONS-2_A-1 THRU E3.0 DON JUAN 704 E PRINCE RD 10-24-24_D2_R1_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
MECH CHECK.PDF DOCUMENTS VIEW
T22CM02430 PLAN REVIEW FEE AND INSPECTION SHEET.DOCX DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
SYSTEMS DESIGN REPORT.PDF DOCUMENTS VIEW