Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM02402
Permit Details
Apply Date:
04/01/2022
Applicant:
Description:
Awning additions to existing buildings
Permit Reviews
Permit Number - T22CM02402
Permit Status: Issued
Permit Description: Awning additions to existing buildings
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/01/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 04/21/2022 | COMPLETED |
05/03/2022 | RESUBMITTAL | 05/10/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM02402
Permit Status: Issued
Permit Description: Awning additions to existing buildings
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
04/16/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
04/16/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
04/16/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/16/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM02402
Permite Description: Awning additions to existing buildings
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM02402
Permit Description: Awning additions to existing buildings
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/18/2023 | COT - LCBU - Framing | Passed | welding of columns to purloins is complete. Roof decking is properly screwed to framing members. | |
01/18/2023 | ENGR Engineering Final | Passed | ||
01/18/2023 | COT - LCBU - Building Final | Passed | canopy is complete |