Permit: T22CM02149
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1128 E ASCENT ST
Address NEW:
1128 E ASCENT ST
Apply Date:
03/23/2022
Applicant:
Celina Rodriguez
Description:
SFR KBME1609 T21-M0008
Conditions
Permit Number - T22CM02149
Permit Status: Issued
Permit Description: SFR KBME1609 T21-M0008
| Date | Description | Comments |
|---|---|---|
| 03/23/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 03/23/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
| 03/23/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 03/23/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM02149
Permite Description: SFR KBME1609 T21-M0008
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | |
| 10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Gas Pressure Test | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 02/27/2023 | RSBU - Building Final | N/A | Re-inspection required | Unable to connect with contractor for inspection. |
| 02/27/2023 | COT - RSEL - Electrical Final | N/A | Re-inspection required | Unable to connect with contractor for inspection. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM02149
Permit Description: SFR KBME1609 T21-M0008
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/14/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 04/14/2022 | COT - RSPL - Sewer | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 04/14/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/14/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 04/27/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 04/27/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 04/27/2022 | COT - RSBU - Preslab | Passed | {Activity date: 04/27/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 04/27/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 04/27/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 04/27/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 04/27/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} | |
| 07/07/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - approved} | |
| 07/07/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - approved} | |
| 11/16/2022 | COT - LCBU - Framing | Passed | ||
| 11/16/2022 | RSME - Mechanical Progress | Passed | ||
| 12/15/2022 | COT - RSEL - Construction Power | Passed | clearance for TEP ECO. | |
| 12/15/2022 | BULD - Electrical Clearance | Passed | clearance for TEP ECO. | |
| 02/14/2023 | COT - BULD - SWG Clearance | Passed | clearance for Southwest Gas | |
| 02/22/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 02/22/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 02/22/2023 | COT - RSME - Mechanical Final | Passed | ||
| 03/01/2023 | RSBU - Building Final | Passed | ||
| 03/01/2023 | COT - RSEL - Electrical Final | Passed |