Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
03/17/2022
Applicant:
Lisa Bowers
Description:
New Restaurant (demo by separate permit)

Permit Reviews

Permit Number - T22CM01960
Permit Status: Complete
Permit Description: New Restaurant (demo by separate permit)
Start Date Submittal Complete Date Status  
03/17/2022 3RD PARTY REVIEW - COMMERCIAL 05/26/2022 COMPLETED Review Details
07/25/2022 RESUBMITTAL 08/18/2022 COMPLETED Review Details
08/18/2022 RESUBMITTAL 08/23/2022 COMPLETED Review Details
08/29/2022 REVISION - - 1ST 09/20/2022 COMPLETED Review Details
02/09/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 02/10/2023 APPROVED Review Details
02/08/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/09/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM01960
Permit Status: Complete
Permit Description: New Restaurant (demo by separate permit)
Date Description Comments
02/08/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
04/25/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
04/25/2022 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
04/25/2022 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/25/2022 SPECIAL INSPECTION IS REQUIRED FOR SOILS.
08/19/2022 Primary roof drainage must not be directed over sidewalks unless sidewalk scuppers are provided. Roof drainage must match the Development Package. Consistent plans must be provided before final inspection.
08/23/2022 Prior to permit issuance a General Contractor Letter (GCL) is required
02/10/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM01960
Permite Description: New Restaurant (demo by separate permit)
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
12/16/2022 COT - LCPL - Gas Pressure Test N/A Canceled
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning N/A Not Ready
10/26/2022 COT - LCPL - Rough Soil N/A Not Ready
02/06/2023 COT - LCPL - Backwater Valve N/A Not Applicable N/A
02/06/2023 COT - LCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable N/A
01/27/2023 COT - LCBU - Building Final N/A Partial Pass Recommend issuing TCO for stocking and training.
01/23/2023 COT - FCON - Fire - Final N/A Not Ready
ENGR Engineering Final N/A Scheduled

Completed Inspections

Permit Status: Complete
Permit Number: T22CM01960
Permit Description: New Restaurant (demo by separate permit)
Total Completed Inspections - 37
Date Description Inspector Results Comments
09/14/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 09/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved}
10/13/2022 COT - LCEL - Electrical Underground Passed {Activity date: 10/13/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 10/12/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NR} ; {Activity date: 09/14/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -Partial Approval: Exterior conduits on East, South, and West sides.}
01/23/2023 COT - FCON - Alarm - Final Passed
11/22/2022 COT - LCBU - Framing Passed
11/30/2022 BULD - Electrical Clearance Passed
11/30/2022 COT - LCEL - Electrical Intermediate Passed
12/08/2022 COT - LCPL - Sewer Passed
12/14/2022 COT - LCPL - Plumbing Intermediate Passed Grease trap.
12/16/2022 COT - LCPL - Gas Pressure Test Passed
12/19/2022 COT - BULD - SWG Clearance Passed Clearance; called in to SW Gas at 1040 hours.
12/20/2022 COT - LCME - Mechanical Above Ceiling Passed
12/20/2022 COT - LCPL - Plumbing Above Ceiling Passed
12/21/2022 COT - LCME - Kitchen Hood Passed
01/11/2023 COT - LCEL - Outdoor Lighting Passed
01/18/2023 COT - LCEL - Electrical Above Ceiling Passed
01/18/2023 COT - LCBU - Building Above Ceiling Passed
01/18/2023 COT - LCME - Mechanical Final Passed Air balance test results forwarded to Robert Sherry
01/18/2023 COT - LCPL - Plumbing Final Passed
01/18/2023 COT - LCEL - Electrical Final Passed
01/23/2023 COT - FCON - Hood System - Final Passed
02/06/2023 COT - LCBU - Excavation/Rebar/Zoning Passed
02/06/2023 COT - LCPL - Rough Soil Passed
02/06/2023 COT - LCBU - Masonry Pregrout Passed
02/06/2023 COT - HCBU - Exterior Clips/Sheathing Passed
02/06/2023 COT - LCBU - Building Final Passed
02/06/2023 COT - LCBU - Roof Nailing Passed
02/07/2023 FCON – OH Piping & Hydro Passed Passed on 11/17/22.
02/06/2023 COT - LCBU - Exterior Clips/Sheathing Passed
02/06/2023 COT - HCBU - Interior Shear Bracing Passed
02/06/2023 COT - FCON - Sprinkler - Final Passed
02/06/2023 COT - LCPL - Plumbing Roof Drains Passed
02/06/2023 COT - LCBU - Stem Wall/Retaining Wall Passed
02/06/2023 COT - LCBU - Preslab Passed
02/06/2023 COT - LCME - Mechanical Intermediate Passed
02/07/2023 COT - FCON - Underground Pressure Passed Completed by J. Fordney on 11/30/22.
02/07/2023 COT - FCON - Fire - Final Passed
02/07/2023 COT - FCON - Underground Flush Passed

Scheduled Inspections

Scheduled Inspections - T22CM01960
Status: Complete
Description: New Restaurant (demo by separate permit)
Scheduled Date Description Entered By Entered Date
02/10/2023 ENGR Engineering Final Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
COMCHECK - INT. + EXT LIGHTING REVISION 1.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GCL.PDF DOCUMENTS VIEW
WILLDAN PSA.PDF DOCUMENTS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW
REV1 PERMIT.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
REV PHOTOMETRIC PLAN.PDF DOCUMENTS VIEW
LIGHTING CUT SHEETS.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
DP FOR REFERENCE ONLY.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF DOCUMENTS VIEW
PORTILLO'S REVISED REPORT_V2.PDF DOCUMENTS VIEW
T22CM01960.PORTILLOS - EL CON MALL SPECIAL INSPECTION-2023-02-03_V1.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW