Permit: T22CM01955
Permit Details
Apply Date:
03/17/2022
Applicant:
Andrew Venne
Description:
TI: Batch Cafe and Bar
Permit Reviews
Permit Number - T22CM01955
Permit Status: Complete
Permit Description: TI: Batch Cafe and Bar
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/17/2022 | COMMERCIAL - TI | 05/11/2022 | COMPLETED |
05/12/2022 | RESUBMITTAL | 06/14/2022 | COMPLETED |
Conditions
Permit Number - T22CM01955
Permit Status: Complete
Permit Description: TI: Batch Cafe and Bar
Date | Description | Comments |
---|---|---|
08/05/2022 | CONTRACTOR LETTER REQUIRED PRIOR TO FINAL INSPECTION |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01955
Permite Description: TI: Batch Cafe and Bar
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Building Progress | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01955
Permit Description: TI: Batch Cafe and Bar
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 06/17/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Waste and vent lines at 2"- 3" lines. Ok to cover progress areas.} | |
07/29/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 07/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/17/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Electric under ground for bar area. Ok to cover progress areas.} | |
07/29/2022 | COT - LCBU - Framing | Passed | {Activity date: 07/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to insulate and drywall progress areas} | |
07/29/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 07/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
07/29/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 07/29/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, mini-splits} | |
11/09/2022 | COT - FCON - Sprinkler - Final | Passed | ||
11/09/2022 | COT - FCON - Fire - Final | Passed | ||
11/10/2022 | COT - LCBU - Building Final | Passed | ||
11/15/2022 | COT - LCBU - CofO | Passed | OK to make application for Certificate of Occupancy |