Permit: T22CM01818
Permit Details
Apply Date:
03/11/2022
Applicant:
Description:
SFR 230.2380 T21-M0028
Outstanding Activity Conditions
Permit Number - T22CM01818
Permit Status: Issued
Permit Description: SFR 230.2380 T21-M0028
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
03/11/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
03/11/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
03/11/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
03/11/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020 100/P21WP00059 IS ACCEPTED AND RELEASED BY PCRWRD AND NO FINAL UNTIL THE DOWNSTREAM PUBLIC SEWERS: G-2020-059/P21WP0060 - LA ESTANCIA DE TUCSON - PHASE II - PARCEL 3, G-2020-089/P21WP00061 - LA ESTANCIA DE TUCSON - PHASE II - PARCEL 4 AND G-20-087 - (OFFSITE) IS ACCEPTED AND RELEASED BY PCRWRD |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM01818
Permite Description: SFR 230.2380 T21-M0028
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM01818
Permit Description: SFR 230.2380 T21-M0028
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/05/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/05/2022 | COT - RSPL - Sewer | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/05/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 05/05/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
05/16/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} | |
05/16/2022 | COT - RSBU - Preslab | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} ; {Activity date: 05/13/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval please place MASA hold-downs if used rebar on hold-downs not per plan UFER not correct} | |
05/16/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} ; {Activity date: 05/13/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
05/16/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/16/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} ; {Activity date: 05/05/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} | |
06/09/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
06/09/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 06/09/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/01/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/01/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/01/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO} | |
08/01/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP. TEP ECO} | |
08/01/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/01/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/22/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} ; {Activity date: 08/19/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE Maintain min 3/8” to edge of sheetrock, do not tear the surface paper, do not counter sink the screws } |
|
12/02/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/05/2022 | COT - BULD - SWG Clearance | Passed | clearance for Southwest Gas. | |
05/23/2023 | COT - RSPL - Plumbing Final | Passed | ||
05/23/2023 | COT - RSME - Mechanical Final | Passed | ||
05/23/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
06/14/2023 | RSBU - Building Final | Passed | ||
06/14/2023 | COT - RSEL - Electrical Final | Passed |