Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
03/11/2022
Applicant:
Ben Smith
Description:
SFR F50B19 T19-M0033

Permit Reviews

Permit Number - T22CM01814
Permit Status: Issued
Permit Description: SFR F50B19 T19-M0033
Start Date Submittal Complete Date Status  
03/01/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/02/2023 APPROVED Review Details

Conditions

Permit Number - T22CM01814
Permit Status: Issued
Permit Description: SFR F50B19 T19-M0033
Date Description Comments
03/11/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
03/11/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD
03/02/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM01814
Permite Description: SFR F50B19 T19-M0033
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSPL - Yard Water Line N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM01814
Permit Description: SFR F50B19 T19-M0033
Total Completed Inspections - 20
Date Description Inspector Results Comments
04/15/2022 COT - RSPL - Sewer Passed {Activity date: 04/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
04/15/2022 COT - RSPL - Rough Soil Passed {Activity date: 04/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
04/21/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 04/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
04/21/2022 COT - RSBU - Preslab Passed {Activity date: 04/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 04/20/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CO
Reinforcing is not correctly placed into HD cup, reinforcing not tied to adobes
Cancel all other inspections

}
04/21/2022 COT - RSEL - Electrical Underground Passed {Activity date: 04/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
04/21/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 04/21/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
06/08/2022 COT - RSBU - Roof Nailing Passed {Activity date: 06/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
10/06/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
1. Install 3rd stud under 3-ply girder truss in front bedroom
2. Secure gas line at furnace
3. Burn in line sets
4. Frame opening to hallway into master bedroom to 37” rough
5. Remove skittle hole in garage & catwalk to AC platform or install light switch and extend AC platform.}
10/06/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO}
10/06/2022 COT - RSEL - Construction Power Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP. TEP ECO}
10/06/2022 RSME - Mechanical Progress Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/06/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 10/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/07/2022 COT - LCBU - Framing Passed {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} ; {Activity date: 10/06/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE}
11/04/2022 COT - RSBU - Exterior Clips/Sheathing Passed
01/06/2023 COT - BULD - SWG Clearance Passed SWG clearance required
02/01/2023 COT - RSEL - Electrical Final Passed
02/01/2023 COT - RSPL - Plumbing Final Passed
02/01/2023 COT - RSME - Mechanical Final Passed
02/01/2023 RSBU - Building Final Passed
02/01/2023 COT - RSEL - Outdoor Lighting Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW
1_PT REPORT-2023-02-01_V1.PDF DOCUMENTS VIEW
1_WASTEWATER_V1.PDF DOCUMENTS VIEW