Permit Number - T22CM01786
Permit Status: Complete
Permit Description: SFR F50A19 T19-M0034
Date Description Comments
03/11/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
03/11/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 ISACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM01786
Permite Description: SFR F50A19 T19-M0034
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Not Ready
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/26/2022 COT - RSEL - Construction Power N/A Not Ready
10/26/2022 COT - RSPL - Yard Water Line N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM01786
Permit Description: SFR F50A19 T19-M0034
Total Completed Inspections - 16
Date Description Inspector Results Comments
05/11/2022 COT - RSPL - Sewer Passed {Activity date: 05/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
05/11/2022 COT - RSPL - Rough Soil Passed {Activity date: 05/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
05/19/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 05/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
05/19/2022 COT - RSBU - Preslab Passed {Activity date: 05/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
05/19/2022 COT - RSEL - Electrical Underground Passed {Activity date: 05/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
05/19/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 05/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
06/23/2022 COT - RSBU - Roof Nailing Passed {Activity date: 06/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
06/23/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 06/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/21/2022 COT - RSPL - Gas Pressure Test Passed
11/04/2022 COT - HCBU - Interior Shear Bracing Passed
01/17/2023 COT - BULD - SWG Clearance Passed SWG clearance required
01/24/2023 COT - RSPL - Plumbing Final Passed
01/24/2023 RSBU - Building Final Passed
01/24/2023 COT - RSEL - Outdoor Lighting Passed
01/24/2023 COT - RSME - Mechanical Final Passed
01/24/2023 COT - RSEL - Electrical Final Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SITE PLAN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW
1_ST SEWER ACCEPTANCE LETTER_V1.PDF DOCUMENTS VIEW