Permit: T22CM01725
Permit Details
Apply Date:
03/09/2022
Applicant:
RAMON VALDEZ
Description:
DUPLEX DUPLVAL82 T22-M0037
Contractors:
- VAL VAL CONSTRUCTION LLC
Permit Reviews
Permit Number - T22CM01725
Permit Status: Final
Permit Description: DUPLEX DUPLVAL82 T22-M0037
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/09/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/31/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM01725
Permit Status: Final
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/09/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T22CM01725
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/31/2022 | PLUMBING - INTERMEDIATE | KEN | Approved | |
| 03/31/2022 | MECHANICAL - INTERMEDIATE | KEN | Approved | |
| 04/05/2022 | PLUMBING - SEWER HCS CONNECT | TGAUSP | Approved | Approved, okay to backfill progress areas |
| 04/05/2022 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | Approved, okay to backfill progress areas |
| 04/05/2022 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved |
| 04/08/2022 | ELECTRIC - UFER | TGAUSP | Approved | Approved |
| 04/08/2022 | BUILDING PRE-SLAB | TGAUSP | Approved | Approved |
| 04/08/2022 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved |
| 04/25/2022 | ROOF NAILING | DMUNIZ | Approved | Approved |
| 04/25/2022 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | Approved |
| 04/28/2022 | RESIDENTIAL INTERMEDIATE | TGAUSP | Approved | Approved unit 1 and 2, okay to insulate and drywall |
| 04/28/2022 | FRAMING | TGAUSP | Approved | Approved |
| 05/20/2022 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE ECO FOR UNITS #1 AND #2 CONSTRUCTION POWER |
| 05/20/2022 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | Approved, please send ECO Clearance to TEP for units #1 and #2 construction power |
| 06/27/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | 1090.Approved |
| 06/27/2022 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
| 06/27/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | 1090.Approved |
| 06/27/2022 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
| 06/27/2022 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |
| 06/27/2022 | FIREWALL/FIREBARRIER/FIRESTOP | TGAUSP | Approved | 1090.Approved |
| 06/27/2022 | BUILDING - FINAL | TGAUSP | Approved | Approved for #1 and #2 |