Permit: T22CM01685
Permit Details
Status:
In Revision
Type:
Residential Building - One or Two Family
Address:
9845 E MURCHISON PL
Address NEW:
9845 E MURCHISON PL
Apply Date:
03/08/2022
Applicant:
Description:
Installation of 12.40KW PV System/Derate to 175A
Permit Reviews
Permit Number - T22CM01685
Permit Status: In revision
Permit Description: Installation of 12.40KW PV System/Derate to 175A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2022 | OTHER | 04/27/2022 | COMPLETED |
| 05/05/2022 | REVISION - - 1ST | 05/24/2022 | COMPLETED |
Conditions
Permit Number - T22CM01685
Permit Status: In revision
Permit Description: Installation of 12.40KW PV System/Derate to 175A
| Date | Description | Comments |
|---|---|---|
| 03/08/2022 | THE INSTALLATION SHALL COMPLY WITH ALL APPLICABLE REQUIREMENTS OF SECTION 605.11.1 THROUGH 605.11.4 OF THE 2012 EDITION OF THE INTERNATIONAL FIRE CODE, THE INTERNATIONAL BUILDING CODE AND NFPA 70. |
Completed Inspections
Permit Status: In Revision
Permit Number: T22CM01685
Permit Description: Installation of 12.40KW PV System/Derate to 175A
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2022 | PDSD Building Division - TEP PMÂ Clearance | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE DGC} | |
| 09/06/2022 | RSBU - Building Final | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
| 09/06/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, please send DGC Clearance to TEP for the solar meter} |