Permit: T22CM01667
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
505 S COLUMBUS BL
Address NEW:
505 S COLUMBUS BL
Apply Date:
03/08/2022
Applicant:
Arturo Elizalde
Description:
Electrical and Plumbing to Meditation Huts T21DV05401
Permit Reviews
Permit Number - T22CM01667
Permit Status: Complete
Permit Description: Electrical and Plumbing to Meditation Huts T21DV05401
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/31/2022 | COMPLETED |
| 05/06/2022 | RESUBMITTAL | 05/09/2022 | COMPLETED |
| 06/02/2022 | RESUBMITTAL | 06/09/2022 | COMPLETED |
| 09/22/2022 | RESUBMITTAL | 10/03/2022 | COMPLETED |
Conditions
Permit Number - T22CM01667
Permit Status: Complete
Permit Description: Electrical and Plumbing to Meditation Huts T21DV05401
| Date | Description | Comments |
|---|---|---|
| 10/03/2022 | General Contractor Letter (GCL) or Owner/Builder Waiver required prior to permit issuance |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01667
Permite Description: Electrical and Plumbing to Meditation Huts T21DV05401
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2023 | RSBU - Building Final | N/A | Re-inspection required | 8/28/23: 1, install landings at all exterior doors 2, remove or secure security door 3, seal all 18"x18" openings in exterior walls 4, wrap line set insulation with UV resistent tape. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01667
Permit Description: Electrical and Plumbing to Meditation Huts T21DV05401
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/22/2023 | COT - RSPL - Rough Soil | Passed | ||
| 02/22/2023 | COT - RSPL - Yard Water Line | Passed | ||
| 02/22/2023 | COT - RSEL - Electrical Underground | Passed | ||
| 03/01/2023 | ENGR Engineering Final | Passed | There was no improvements done on the outside so I went ahead and passed it | |
| 03/03/2023 | COT - RSPL - Plumbing Final | Passed | 3/3/23 Items noted on last inspection have been corrected. | |
| 03/03/2023 | COT - RSEL - Electrical Final | Passed | 3/3/23 Electrical outlets are complete. Electrical outlets in storage building have been removed. | |
| 08/16/2023 | COT - RSME - Mechanical Final | Passed | Mini-splits are installed and operational on all 5 units. Okay to issue Certificates of Completion. | |
| 09/01/2023 | RSBU - Building Final | Passed | 9/1/23: all corrections made |