Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
03/08/2022
Applicant:
Arturo Elizalde
Description:
Electrical and Plumbing to Meditation Huts T21DV05401

Permit Reviews

Permit Number - T22CM01667
Permit Status: Complete
Permit Description: Electrical and Plumbing to Meditation Huts T21DV05401
Start Date Submittal Complete Date Status  
03/08/2022 RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO 03/31/2022 COMPLETED Review Details
05/06/2022 RESUBMITTAL 05/09/2022 COMPLETED Review Details
06/02/2022 RESUBMITTAL 06/09/2022 COMPLETED Review Details
09/22/2022 RESUBMITTAL 10/03/2022 COMPLETED Review Details

Conditions

Permit Number - T22CM01667
Permit Status: Complete
Permit Description: Electrical and Plumbing to Meditation Huts T21DV05401
Date Description Comments
10/03/2022 General Contractor Letter (GCL) or Owner/Builder Waiver required prior to permit issuance

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM01667
Permite Description: Electrical and Plumbing to Meditation Huts T21DV05401
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/28/2023 RSBU - Building Final N/A Re-inspection required 8/28/23: 1, install landings at all exterior doors 2, remove or secure security door 3, seal all 18"x18" openings in exterior walls 4, wrap line set insulation with UV resistent tape.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM01667
Permit Description: Electrical and Plumbing to Meditation Huts T21DV05401
Total Completed Inspections - 8
Date Description Inspector Results Comments
02/22/2023 COT - RSPL - Rough Soil Passed
02/22/2023 COT - RSPL - Yard Water Line Passed
02/22/2023 COT - RSEL - Electrical Underground Passed
03/01/2023 ENGR Engineering Final Passed There was no improvements done on the outside so I went ahead and passed it
03/03/2023 COT - RSPL - Plumbing Final Passed 3/3/23 Items noted on last inspection have been corrected.
03/03/2023 COT - RSEL - Electrical Final Passed 3/3/23 Electrical outlets are complete. Electrical outlets in storage building have been removed.
08/16/2023 COT - RSME - Mechanical Final Passed Mini-splits are installed and operational on all 5 units. Okay to issue Certificates of Completion.
09/01/2023 RSBU - Building Final Passed 9/1/23: all corrections made

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW