Permit: T22CM01665
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
825 N 3RD AV
Address NEW:
825 N 3RD AV
Apply Date:
03/08/2022
Applicant:
Robert Knodle
Description:
Replace Window with Door; Renovate Chimney and Relocate Water Heater
Permit Reviews
Permit Number - T22CM01665
Permit Status: Inspections
Permit Description: Replace Window with Door; Renovate Chimney and Relocate Water Heater
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/02/2022 | COMPLETED |
| 08/29/2022 | RESUBMITTAL | 08/31/2022 | COMPLETED |
Conditions
Permit Number - T22CM01665
Permit Status: Inspections
Permit Description: Replace Window with Door; Renovate Chimney and Relocate Water Heater
| Date | Description | Comments |
|---|---|---|
| 09/02/2022 | General Contractor Letter (GCL) or Owner/Builder Waiver required prior to permit issuance |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T22CM01665
Permite Description: Replace Window with Door; Renovate Chimney and Relocate Water Heater
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/30/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 08/30/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 10/26/2022 | COT - RSBU - Roof Nailing | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Preslab | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections
Permit Number: T22CM01665
Permit Description: Replace Window with Door; Renovate Chimney and Relocate Water Heater
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | mechanical, electrical, and plumbing rough in are complete. | |
| 02/24/2023 | COT - RSPL - Rough Soil | Passed | ||
| 02/24/2023 | COT - RSPL - Gas Pressure Test | Passed | holding 15# of air. | |
| 02/24/2023 | COT - BULD - SWG Clearance | Passed | passed gas line pressure test. | |
| 03/21/2023 | COT - LCBU - Framing | Passed | ||
| 07/30/2024 | COT - RSME - Mechanical Final | Passed | ||
| 07/30/2024 | RSBU - Building Final | Passed | ||
| 07/30/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 07/30/2024 | COT - RSEL - Electrical Final | Passed |