Permit Details

Status:
Issued
Type:
Commercial Building
Address:
343 S SCOTT AV
Apply Date:
03/04/2022
Applicant:
Lisa Bowers
Description:
Interior only remodel of existing multi-family townhomes

Permit Reviews

Permit Number - T22CM01601
Permit Status: Issued
Permit Description: Interior only remodel of existing multi-family townhomes
Start Date Submittal Complete Date Status  
03/04/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 04/05/2022 COMPLETED Review Details
06/16/2022 RESUBMITTAL 10/20/2022 COMPLETED Review Details
10/20/2022 RESUBMITTAL 10/20/2022 ACTIVE Review Details
02/07/2023 COMMERCIAL REVIEW - FULL v.3 03/08/2023 APPROVED Review Details
08/21/2023 COMMERCIAL REVIEW - FULL v.1 08/31/2023 APPROVED Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 11/29/2022 REQUIRES RESUBMIT Review Details
12/12/2022 COMMERCIAL REVIEW - FULL v.2 01/30/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM01601
Permit Status: Issued
Permit Description: Interior only remodel of existing multi-family townhomes
Date Description Comments
07/20/2023 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
01/04/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
03/08/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
01/04/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM01601
Permite Description: Interior only remodel of existing multi-family townhomes
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
07/27/2023 COT - HCEL - Electrical Above Ceiling N/A Partial Pass Units 3, 4, 5.
07/27/2023 COT - HCEL - Electrical Intermediate N/A Partial Pass Units 3, 4, 5 are complete
08/09/2023 COT - HCBU - Building Final N/A Not Ready 8/9/23: Not ready
08/09/2023 COT - HCEL - Electrical Progress N/A Partial Pass 8/9/23: unit 6 passed
08/09/2023 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 8/9/23: unit 6 passed
08/09/2023 COT - HCPL - Plumbing Progress N/A Partial Pass 8/9/23: unit 6 passed
08/11/2023 COT - HCME - Mechanical Intermediate N/A Canceled 8/11/2023 canceled per contractor
08/09/2023 COT - HCME - Mechanical Progress N/A Not Ready 8/9/23: unit 6 not ready
08/09/2023 COT - HCPL - Plumbing Intermediate N/A Partial Pass 8/9/23: unit 6 passed
08/09/2023 COT - HCBU - Building Above Ceiling N/A Partial Pass 8/9/23: unit 6 electrical and plumbing passed, mechanical not ready
07/27/2023 COT - HCBU - Building Progress N/A Partial Pass Units 3, 4, 5.
COT - FCON - Sprinkler - Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM01601
Permit Description: Interior only remodel of existing multi-family townhomes
Total Completed Inspections - 7
Date Description Inspector Results Comments
07/27/2023 COT - HCBU - Framing Passed Units 3, 4, 5, are complete.
08/11/2023 COT - HCPL - Sewer Passed Approved. Okay to backfill. Shading required. 8/11/2023
03/11/2024 COT - HCEL - Electrical Final Passed OK to set electric meters for units #5, #6, and,House panel. Called clearance in to TEP at 1235 hour. Code,ECO.
05/01/2024 COT - HCBU - Building Progress Passed Interior intermediates. Ok to insulate and sheet rock walls and ceilings.
11/08/2024 COT - FCON - Alarm - Final Passed Passed via FCP permit
06/10/2024 COT - FCON - Fire - Final Passed
11/08/2024 COT - FCON - Sprinkler - Final Passed Passed via FCP permit

Documents

File Name Document Type  
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV1_PLAN SET_V1.PDF DOCUMENTS VIEW
REV3 SCOPE MEMO 8-15-23_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
343 S SCOTT AVE - SPECIAL DISTRICTS APPLICATION ATTACHMENTS 12-14-2022_V1.PDF DOCUMENTS VIEW
6_COMMENT NARRATIVE_V1.PDF DOCUMENTS VIEW
CONS-6_PLAN SET_V2.PDF DOCUMENTS VIEW
GLENWOOD TOWNHOUSES - 2ND CITY COMMENTS RESPONSE LETTER - 11 15 22_V2.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_STRUCTURAL CALCULATIONS_V1.PDF DOCUMENTS VIEW
1_UNIT 1 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
1_UNIT 2 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
1_UNIT 3 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
1_UNIT 4 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
1_UNIT 5 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
1_UNIT 6 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE_V1.PDF DOCUMENTS VIEW
2_UNIT 1 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
2_UNIT 2 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
2_UNIT 3 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
2_UNIT 4 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
2_UNIT 5 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
2_UNIT 6 HVAC LOAD CALCULATION_V1.PDF DOCUMENTS VIEW
CONS-1_PLAN SET_V1.PDF DOCUMENTS VIEW
CONS-2_PLAN SET_V1.PDF DOCUMENTS VIEW