Permit: T22CM01478
Permit Details
Apply Date:
03/01/2022
Applicant:
Brent Stevens
Description:
North 11 Car Garage
Permit Reviews
Permit Number - T22CM01478
Permit Status: Complete
Permit Description: North 11 Car Garage
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/01/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/02/2022 | COMPLETED |
06/30/2022 | RESUBMITTAL | 07/19/2022 | COMPLETED |
08/12/2022 | RESUBMITTAL | 08/29/2022 | COMPLETED |
09/13/2022 | RESUBMITTAL | 09/26/2022 | COMPLETED |
10/03/2022 | RESUBMITTAL | 10/06/2022 | COMPLETED |
Conditions
Permit Number - T22CM01478
Permit Status: Complete
Permit Description: North 11 Car Garage
Date | Description | Comments |
---|---|---|
10/06/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
10/06/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
10/06/2022 | SHOP DRAWINGS REQUIRED FOR WOOD FLOOR JOISTS. | |
10/06/2022 | SHOP DRAWINGS REQUIRED FOR TRUSSES, WOOD ROOF TRUSSES. | |
10/06/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01478
Permite Description: North 11 Car Garage
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/12/2023 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
01/24/2024 | COT - LCEL - Service Upgrade | N/A | Partial Pass | 1/23/24: bond/bushing on raceway must be properly grounded to panel with listed means. 1/24/24: GARG 2 ECO TEP clearance |
01/09/2024 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
10/27/2022 | ENGR Engineering Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01478
Permit Description: North 11 Car Garage
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/14/2023 | COT - HCEL - Grounding/Bonding | Passed | North end 11 Car Garage building. UFER is in place. 3/14/2023 | |
05/03/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 5-3-23: Concrete slabs for garages are complete. | |
05/03/2023 | COT - LCBU - Preslab | Passed | 5-3-23: All garage floors are complete. | |
05/03/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | Exterior sheathing is properly nailed off. Shear wall clips and rafter clips are properly nailed. | |
05/03/2023 | COT - LCBU - Roof Nailing | Passed | ||
06/12/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
06/12/2023 | COT - LCBU - Framing | Passed | ||
08/07/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
08/07/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
01/19/2024 | COT - LCEL - Electrical Underground | Passed | ||
02/13/2024 | COT - LCEL - Service Upgrade | Passed | ||
02/13/2024 | COT - LCBU - Building Final | Passed | ||
02/13/2024 | COT - LCEL - Electrical Progress | Passed | ||
02/13/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
02/13/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
02/13/2024 | COT - LCBU - Building Progress | Passed | ||
02/13/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
02/13/2024 | PDSD Building Division - Sign Final | Passed | ||
02/13/2024 | COT - LCEL - Electrical Final | Passed | ||
05/16/2024 | ENGR Engineering Final | Passed | ||
05/17/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
05/17/2024 | PDSD Site/Engineering Division - NPPO | Passed |