210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg

Permit Reviews

Permit Number - T22CM01449
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg
Start Date Submittal Complete Date Status  
03/01/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 05/02/2022 COMPLETED Review Details
06/30/2022 RESUBMITTAL 07/19/2022 COMPLETED Review Details
08/12/2022 RESUBMITTAL 08/29/2022 COMPLETED Review Details
09/13/2022 RESUBMITTAL 09/26/2022 COMPLETED Review Details
10/03/2022 RESUBMITTAL 10/06/2022 COMPLETED Review Details
01/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/18/2024 APPROVED Review Details

Conditions

Permit Number - T22CM01449
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg
Date Description Comments
10/06/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/06/2022 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
10/06/2022 SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION.
10/06/2022 SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION.
10/06/2022 SHOP DRAWINGS REQUIRED FOR WOOD FLOOR JOISTS.
10/06/2022 SHOP DRAWINGS REQUIRED FOR TRUSSES, WOOD ROOF TRUSSES.
10/06/2022 PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE
10/14/2022 PCRWRD requests that the City of Tucson, add the PCRWRD Condition to the COT building permit #T22CM01449:ISSUED WITH PCRWRD CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE DISCHARGE AUTHORIZATION IS ISSUED BY PDEQ FOR THE PRIVATE SEWER #P22SD00039 Gerry KoziolPima County DSD-Building Codes/Wastewater Utility Fee201 N Stone Ave Tucson, AZ 85701(520)724-6503

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM01449
Permite Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg
Total Outstanding Inspections - 11
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCEL - Electrical Underground N/A Not Ready
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning N/A Not Ready
10/26/2022 COT - LCBU - Sustainability N/A Not Ready
04/11/2023 COT - LCPL - Backwater Valve N/A Not Applicable
04/11/2023 COT - LCPL - Gas Pressure Test N/A Not Applicable
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
10/26/2022 COT - FCON - Sprinkler - Final N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
03/15/2023 FCON – OH Piping & Hydro N/A Partial Pass building A done

Completed Inspections

Permit Status: Complete
Permit Number: T22CM01449
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities. Bldg
Total Completed Inspections - 31
Date Description Inspector Results Comments
11/14/2022 COT - LCPL - Rough Soil Passed Bldg 1, okay to backfill progress area
03/15/2023 COT - HCBU - Interior Shear Bracing Passed
03/15/2023 COT - LCBU - Exterior Clips/Sheathing Passed
03/22/2023 COT - LCPL - Plumbing Progress Passed
03/22/2023 COT - LCEL - Electrical Above Ceiling Passed
03/22/2023 COT - LCME - Mechanical Above Ceiling Passed
03/22/2023 COT - LCPL - Plumbing Above Ceiling Passed
03/22/2023 COT - LCME - Mechanical Progress Passed
03/22/2023 COT - LCBU - Framing Passed
03/22/2023 COT - LCBU - Building Above Ceiling Passed
04/11/2023 COT - LCME - Mechanical Intermediate Passed
04/11/2023 COT - LCPL - Plumbing Intermediate Passed
04/11/2023 COT - LCPL - Plumbing Roof Drains Passed
04/11/2023 COT - LCBU - Preslab Passed
04/11/2023 COT - LCBU - Firewall/Fire Barrier/Firestop Passed
04/11/2023 COT - LCEL - Electrical Intermediate Passed
04/11/2023 COT - LCPL - Sewer Passed
04/11/2023 COT - LCBU - Roof Nailing Passed
12/12/2023 COT - LCBU - Building Progress Passed 12/12/23: permit extension.
01/09/2024 COT - LCEL - Service Upgrade Passed 1/9/24 units HBA1, 1101,1102, 1103, 1104, 1201, 1202, 1203, 1204, 1301, 1302, 1303, 1304
01/16/2024 BULD - Electrical Clearance Passed HPA1 ECO
01/16/2024 COT - LCEL - Electrical Progress Passed
02/06/2024 COT - FCON - Fire - Final Passed
02/06/2024 COT - FCON - Sprinkler - Final Passed
02/06/2024 COT - FCON - Alarm - Final Passed
02/08/2024 COT - LCEL - Electrical Final Passed
02/08/2024 COT - LCPL - Plumbing Final Passed
02/08/2024 COT - LCME - Mechanical Final Passed
05/16/2024 COT - LCEL - Outdoor Lighting Passed
05/15/2024 FCON – OH Piping & Hydro Passed
05/17/2024 COT - LCBU - Building Final Passed Ok for LEVEL 4 TCO
5/17/24: ok for CofO at building 1