Permit: T22CM01266
Permit Details
Apply Date:
02/22/2022
Applicant:
Andrea Flood
Description:
SFR F50B19 T19-M0033
Outstanding Activity Conditions
Permit Number - T22CM01266
Permit Status: Issued
Permit Description: SFR F50B19 T19-M0033
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
02/22/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
02/22/2022 | NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM01266
Permite Description: SFR F50B19 T19-M0033
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/19/2023 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM01266
Permit Description: SFR F50B19 T19-M0033
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/11/2022 | COT - RSPL - Sewer | Passed | {Activity date: 03/11/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
03/11/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/11/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
03/22/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/22/2022 | COT - RSBU - Preslab | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/22/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
03/22/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/10/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO} | |
10/10/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP. TEP ECO} | |
10/10/2022 | RSME - Mechanical Progress | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/10/2022 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} | |
10/12/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 10/10/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - . DE 1. Post girder in garage 2. Vents are dry 3. Secure gas line @ laundry 4. Hallway openings are required to be min 37” at rough frame} |
|
10/12/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/11/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval ok to cover no pressure test} | |
11/04/2022 | COT - LCBU - Framing | Passed | ||
11/04/2022 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
01/19/2023 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
04/03/2023 | COT - RSEL - Electrical Final | Passed | ||
04/03/2023 | COT - RSME - Mechanical Final | Passed | ||
04/03/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
04/11/2023 | COT - RSPL - Plumbing Final | Passed | ||
04/24/2023 | RSBU - Building Final | Passed |