Permit: T22CM01177
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
475 S GOLLOB RD
Address NEW:
475 S GOLLOB RD
Apply Date:
02/16/2022
Applicant:
Brian Hagedon
Description:
R-Addition of a Master Suite bathroom(s) and Garage
Permit Reviews
Permit Number - T22CM01177
Permit Status: Inspections
Permit Description: R-Addition of a Master Suite bathroom(s) and Garage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/16/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/05/2022 | COMPLETED |
| 04/06/2022 | RESUBMITTAL | 04/25/2022 | COMPLETED |
Conditions
Permit Number - T22CM01177
Permit Status: Inspections
Permit Description: R-Addition of a Master Suite bathroom(s) and Garage
| Date | Description | Comments |
|---|---|---|
| 03/31/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T22CM01177
Permite Description: R-Addition of a Master Suite bathroom(s) and Garage
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
| 04/10/2023 | COT - RSPL - Sewer | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Rough Soil | N/A | Not Ready | |
| 10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
| 11/14/2023 | RSME - Mechanical Progress | N/A | Partial Pass | Large storage room, pantry room, and connecting hallway. Electrical lines and mechanical is in place. Okay to proceed progress areas. 11/14/2023 |
Completed Inspections
Permit Status: Inspections
Permit Number: T22CM01177
Permit Description: R-Addition of a Master Suite bathroom(s) and Garage
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/24/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/20/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor} ; {Activity date: 05/20/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} | |
| 06/07/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 06/22/2022 | COT - RSBU - Preslab | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 06/22/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 06/22/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/17/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for stem wall, ok to grout} ; {Activity date: 06/07/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Exterior continuous footings for stem wall ok for concrete placement} | |
| 10/07/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 10/07/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 10/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 01/20/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 05/19/2023 | COT - RSPL - Sewer | Passed | ||
| 11/14/2023 | COT - RSPL - Rough Soil | Passed | ||
| 11/05/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 05/01/2025 | COT - LCBU - Framing | Passed | passed 6/1/25 | |
| 05/01/2025 | RSME - Mechanical Progress | Passed | vent installed | |
| 04/24/2026 | COT - RSME - Mechanical Final | Passed | Passed | |
| 04/24/2026 | COT - RSPL - Plumbing Final | Passed | Passed |