Permit: T22CM01110
Permit Details
Apply Date:
02/14/2022
Applicant:
SUNSET WEST CONSTRUCTION LLC
Description:
DUPLEX SWDUPLEXM T20-M0002
Contractors:
- SUNSET WEST CONSTRUCTION LLC
Permit Reviews
Permit Number - T22CM01110
Permit Status: Final
Permit Description: DUPLEX SWDUPLEXM T20-M0002
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/09/2022 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T22CM01110
Permit Description: DUPLEX SWDUPLEXM T20-M0002
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/17/2022 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | AP 9:00 FaceTime. 9:03; unavailable with Duo, sent invite. No answer with FaceTime. MESSAGES: OLIVER 520-631-8856 |
| 03/17/2022 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | -DE. Unable to connect with contractor for inspection. 9:00 FaceTime. 9:03; unavailable with Duo, sent invite. No answer with FaceTime. MESSAGES: OLIVER 520-631-8856 |
| 03/25/2022 | BUILDING PRE-SLAB | TLUNDBERG | Approved | AP |
| 03/25/2022 | EXCAVATION/LAYOUT REBAR & ZON | TLUNDBERG | Approved | AP |
| 05/02/2022 | FRAMING | DMUNIZ | Approved | Approved |
| 05/02/2022 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | Approved |
| 05/20/2022 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | AP 1533 S JEFFERSON AV #1 #2 |
| 07/15/2022 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE ECO UNITS #1 AND #2 |
| 07/15/2022 | ELECTRIC - UFER | TGAUSP | Approved | Approved |
| 07/15/2022 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | Approved, please send ECO Clearance to TEP for units #1 and #2, construction power |
| 08/26/2022 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | Approved |
| 09/08/2022 | MECHANICAL - FINAL | RCHANDLER | Approved | Approved |
| 09/08/2022 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | Approved |
| 09/08/2022 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | Approved |
| 09/08/2022 | PLUMBING - FINAL | RCHANDLER | Approved | Approved |
| 09/08/2022 | ELECTRIC - FINAL | RCHANDLER | Approved | Approved |
| 09/08/2022 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | Approved |
| 09/08/2022 | BUILDING - FINAL | RCHANDLER | Approved | Approved |
| 09/08/2022 | RESIDENTIAL INTERMEDIATE | RCHANDLER | Approved | Approved |
| 09/08/2022 | FIREWALL/FIREBARRIER/FIRESTOP | RCHANDLER | Approved | Approved |
| 09/08/2022 | ROOF NAILING | RCHANDLER | Approved | Approved |