Permit Details

Status:
Final
Type:
SINGLE FAMILY OTHER
Address NEW:
6206 S PARK AV #01
Apply Date:
02/10/2022
Applicant:
Mike Asher
Description:
gas line clearance and pressure test
Contractors:
  • Mike Asher

Completed Inspections

Permit Status: Final
Permit Number: T22CM01041
Permit Description: gas line clearance and pressure test
Total Completed Inspections - 4
Date Description Inspector Results Comments
02/16/2022 GAS CLEARANCE TGAUSP Approved CODE GAS UNIT#01
02/16/2022 PLUMBING - FINAL TGAUSP Approved Approved
02/16/2022 PLUMBING - GAS RECONNECT TGAUSP Approved Approved, clearance was called into SWG at 10:50am for unit #01
02/16/2022 PLUMBING - GAS PRESSURE TEST TGAUSP Approved Approved